A scrum master assumes a project that is essential to organizational growth. The project is expected to be in production for three years. What should the scrum master do first?

A.
Work with the customers to build the product backlog and identify their initial requirements.
Answers
A.
Work with the customers to build the product backlog and identify their initial requirements.
B.
Meet with the stakeholders and enterprise architects to understand the project's vision.
Answers
B.
Meet with the stakeholders and enterprise architects to understand the project's vision.
C.
Plan and execute a sprint 0 to establish the project's foundational needs.
Answers
C.
Plan and execute a sprint 0 to establish the project's foundational needs.
D.
Create a backlog, and execute a sprint 1 to quickly deliver value to the customers.
Answers
D.
Create a backlog, and execute a sprint 1 to quickly deliver value to the customers.
Suggested answer: A