Question 113 - PMI-ACP discussion
An agile project manager notices that the product owner manages team members' day-to-day tasks in a way that distracts them from their core responsibilities. In addition, the team believes that their questions on product backlog prioritization are not being answered on time.
What should the agile project manager do?
A.
Discuss and address this in the iteration retrospective.
B.
Let the product owner know it is the project manager's responsibility to drive a team's tasks
C.
Discuss the roles and responsibilities of the project team with the product owner.
D.
Ask the product owner to work extra hours to answer the team's questions.