An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate US$40,000 more than expected for the quarter.

What should the agile team do?

A.
Adhere to the new deadline and immediately advise the client that the schedule has been expedited
Answers
A.
Adhere to the new deadline and immediately advise the client that the schedule has been expedited
B.
Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.
Answers
B.
Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.
C.
Submit a change request to the client with a 50% increase in charges due to the new potential profit.
Answers
C.
Submit a change request to the client with a 50% increase in charges due to the new potential profit.
D.
Request additional resources to meet the expedited deadline and obtain training for the new resources.
Answers
D.
Request additional resources to meet the expedited deadline and obtain training for the new resources.
Suggested answer: D