Stakeholders ate displeased with the latest release o! a product's software While most stakeholders attended every sprint review they were otherwise largely uninvolved in the project What should the agile practitioner have done to ensure stakeholder satisfaction?
A.
Communicated early and often, as outlined in the communications matrix
B.
Ensured engagement among stakeholders and the product owner
C.
Conducted additional stakeholder reviews and demos
D.
Worked with the product owner to prioritize user stories