Question 132 - PMI-ACP discussion

Report
Export

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted there is no value to the customers during this iteration What must the agile practitioner do?

A.
Add the new change request as a new user story in the product backlog for the upcoming iteration
Answers
A.
Add the new change request as a new user story in the product backlog for the upcoming iteration
B.
Evaluate the impact of the change request and let the team and product owner decide and reprioritize based on value
Answers
B.
Evaluate the impact of the change request and let the team and product owner decide and reprioritize based on value
C.
Recommend cancelling the current iteration and plan the change request into the next iteration
Answers
C.
Recommend cancelling the current iteration and plan the change request into the next iteration
D.
Recommend that the product owner add this change request as a user story to me backlog tor the current aeration
Answers
D.
Recommend that the product owner add this change request as a user story to me backlog tor the current aeration
Suggested answer: B
asked 23/09/2024