Question 135 - PMI-ACP discussion
A learn member on a new scrum project previously provided support lo another application Due to issues with that application the team member's former supervisor continues assigning them tasks related to that protect The new project's scrum master includes this issue in the risk register.
What should the scrum master do next?
A.
Monitor the threats and risks while allowing the team member to multitask on both projects
B.
Assign more resources to the sprints to compensate for the absences of the team member
C.
Ensure that the threats and risks are communicated and addressed
D.
Assign fewer stones to the sprints so that the team member can still meet sprint goals