An agile practitioner wants to ensure that stakeholders have current information about a project's progress What should the agile practitioner do?

A.
Regularly circulate an updated, detailed version of the project plan
Answers
A.
Regularly circulate an updated, detailed version of the project plan
B.
Frequently update the online project management office (PMO) repository site
Answers
B.
Frequently update the online project management office (PMO) repository site
C.
invite the stakeholders to daily stand ups
Answers
C.
invite the stakeholders to daily stand ups
D.
Post a project board in an area where all can view it.
Answers
D.
Post a project board in an area where all can view it.
Suggested answer: D