A learn using Kanban identifies mat their cycle time has significant variation After brainstorming, the team determines that the root cause is the stones' varying sizes and risks What should the team do?
A.
Reduce work in progress (W1P) limits to accommodate slack for riskier stories
B.
Create a triage step on the Kanban board to pre-identify risky stones
C.
Set a policy lo break down stories larger than a specified complexity, then adjust the WIP
D.
Create a dedicated overflow swimlane on the Kanban board for stones that are loo large