Two similar stories A and B. are estimated at 3 story points Story C. is estimated a( 8 points Alter an iteration in which A and C were completed it is found that story A took much longer than story C.
What should the agile practitioner do?
A.
Assign story B more than 8 story points so to provide a better estimate
B.
Add points to story B's iteration to account for the error but keep story B at 3 points
C.
Assign more resources to story B to bring it in line with the estimate
D.
Reestimate all stories including values for A B and C