When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents How should the agile practitioner address this concern?

A.
Educate the QA manager that in agile, quality is integrated from the begining to end of the project.
Answers
A.
Educate the QA manager that in agile, quality is integrated from the begining to end of the project.
B.
Write backlog items that include QA as part of the description.
Answers
B.
Write backlog items that include QA as part of the description.
C.
Ask for the current QA documents and incorporate them into the technical debt backlog.
Answers
C.
Ask for the current QA documents and incorporate them into the technical debt backlog.
D.
Ask the product owner to write tests and QA controls into the acceptance criteria
Answers
D.
Ask the product owner to write tests and QA controls into the acceptance criteria
Suggested answer: A