A client slates that a product is not being built as requested. How should the agile team address this?

A.
Conduct an internal review to validate functionality before shipping
Answers
A.
Conduct an internal review to validate functionality before shipping
B.
Audit the quality control process to ensure that the product adheres to requirements.
Answers
B.
Audit the quality control process to ensure that the product adheres to requirements.
C.
Lengthen iterations to ensure there is sufficient time to build functionality
Answers
C.
Lengthen iterations to ensure there is sufficient time to build functionality
D.
Hold product review sessions with the client to obtain product acceptance.
Answers
D.
Hold product review sessions with the client to obtain product acceptance.
Suggested answer: B