Question 203 - PMI-ACP discussion
The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this What should the team do next?
A.
Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints.
B.
Add risk mitigation time to each requirement.
C.
Apply the 80/20 rule, reserving 20 percent of each sprints capacity for risk mitigation.
D.
Hold all risks until they become issues, then add issue resolution tasks to the product backlog