An agile team member identifies a potential problem within the project team How should the team's coach react?
A.
Document the problem escalate to the project manager, and develop a solution for the team
B.
Add the problem to the backlog and assign resolution to a future iteration
C.
Instruct the team to try to solve the problem within the team
D.
Perform root cause analysis and report the problem to the product owner