Which is a true statement about PRINCE2 event-driven controls?

A.
Event-driven controls take place at predefined periodic intervals
Answers
A.
Event-driven controls take place at predefined periodic intervals
B.
Event-driven controls are produced at the frequency defined in a Work Package
Answers
B.
Event-driven controls are produced at the frequency defined in a Work Package
C.
Event-driven controls are used for decision making
Answers
C.
Event-driven controls are used for decision making
D.
Checkpoint Reports are event-driven controls
Answers
D.
Checkpoint Reports are event-driven controls
Suggested answer: C

Explanation:

PRINCE2 defines event-driven controls as those that are triggered by the occurrence of certain events within the project lifecycle, such as the completion of a product or phase. These controls are essential for decision-making because they provide necessary information at key points, allowing project managers and the Project Board to make informed decisions about the future of the project.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources