Question 149 - PRINCE2-7-Foundation discussion

Report
Export

Which is created during the Starting up a Project process?

A.
Project mandate
Answers
A.
Project mandate
B.
Project management team role descriptions
Answers
B.
Project management team role descriptions
C.
Communication Management Strategy
Answers
C.
Communication Management Strategy
D.
Quality Register
Answers
D.
Quality Register
Suggested answer: B

Explanation:

During the Starting up a Project process, one of the key activities is to create role descriptions for the project management team. This ensures that everyone involved understands their responsibilities and the expectations placed upon them before the project commences.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.