List of questions
Related questions
Question 8 - PRINCE2-7-Foundation discussion
Which is NOT considered when defining risk tolerance?
A.
A Project Board's attitude towards risk taking
B.
The allocated risk budget
C.
An organization's risk appetite
D.
The amount of risk a Project Board considers acceptable