How many management stages should a PRINCE2 project consist of?

A.
Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
Answers
A.
Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B.
Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
Answers
B.
Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C.
Initiation stage and at least one other management stage to cover the remainder of the project
Answers
C.
Initiation stage and at least one other management stage to cover the remainder of the project
D.
Start up stage, initiation stage and a closing stage
Answers
D.
Start up stage, initiation stage and a closing stage
Suggested answer: A

Explanation:

A PRINCE2 project should consist of a start-up stage, an initiation stage, and at least one other management stage to cover the remainder of the project. This structure ensures that the project is properly initiated and planned before entering into a series of management stages where the work is executed and completed, followed by a closing stage.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources