Which is the definition of a requirement?

A.
A need or expectation that has been documented in an approved management product
Answers
A.
A need or expectation that has been documented in an approved management product
B.
An event relevant to the project that requires project management consideration
Answers
B.
An event relevant to the project that requires project management consideration
C.
A prediction about future performance made by studying historical data and past patterns
Answers
C.
A prediction about future performance made by studying historical data and past patterns
D.
An uncertain event that, should it occur, will have an effect on the project.
Answers
D.
An uncertain event that, should it occur, will have an effect on the project.
Suggested answer: A

Explanation:

A requirement in the context of PRINCE2 is defined as a documented need or expectation that is formally approved and used as a basis for further project development. This documentation typically includes specific details about project scope, expected outcomes, and performance criteria, which are crucial for project planning and execution.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation