The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.

Which principle is the project board applying?

A.
Manage by exception
Answers
A.
Manage by exception
B.
Manage by stages
Answers
B.
Manage by stages
C.
Ensure continued business Justification
Answers
C.
Ensure continued business Justification
D.
Focus on products
Answers
D.
Focus on products
Suggested answer: C

Explanation:

The principle of 'Ensure continued business justification' in PRINCE2 requires that the project remains justified throughout its lifecycle. By reviewing the benefits management approach to ensure it includes sufficient benefit reviews after the project's closure, the project board is applying this principle to confirm that the project continues to provide value and that its benefits are realized as planned, even post-project.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation