List of questions
Related questions
Question 376 - PRINCE2-7-Foundation discussion
The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.
Which principle is the project board applying?
A.
Manage by exception
B.
Manage by stages
C.
Ensure continued business Justification
D.
Focus on products
Your answer: