Which is a purpose of the Managing Product Delivery process?

A.
Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
Answers
A.
Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
B.
Provide a controlled link between the Project Manager and the Team Manager(s)
Answers
B.
Provide a controlled link between the Project Manager and the Team Manager(s)
C.
Enable the Project Board to request updates to the current Team Plan
Answers
C.
Enable the Project Board to request updates to the current Team Plan
D.
Establish solid foundations for the project
Answers
D.
Establish solid foundations for the project
Suggested answer: B

Explanation:

The purpose of the Managing Product Delivery process is to ensure that there is a controlled link between the Project Manager and the Team Managers. This link facilitates the proper execution and delivery of Work Packages, ensuring that work is carried out effectively, monitored, and controlled.

Reference: PRINCE2 Foundation official documentation and study materials.