Identify the missing words in the following sentence.

The project manager [ ? ] for day-to-day management of the project.

A.
and the project board are responsible
Answers
A.
and the project board are responsible
B.
and the team manager(s) are accountable
Answers
B.
and the team manager(s) are accountable
C.
has responsibility
Answers
C.
has responsibility
D.
decides who is responsible
Answers
D.
decides who is responsible
Suggested answer: C

Explanation:

The correct phrase that completes the sentence is 'The project manager has responsibility for day-to-day management of the project.' This highlights the project manager's role in overseeing the project's daily operations, ensuring that project activities align with the overall plan and objectives.

Reference: PRINCE2 7 Foundation Handbook and official training materials.