What may be funded from a risk budget?

A.
Corrections required due to off-specifications
Answers
A.
Corrections required due to off-specifications
B.
Impact analysis of requests for change
Answers
B.
Impact analysis of requests for change
C.
Implementation of a fallback plan
Answers
C.
Implementation of a fallback plan
D.
Preparation of the risk management approach
Answers
D.
Preparation of the risk management approach
Suggested answer: C

Explanation:

A risk budget may fund the implementation of a fallback plan, which is activated if a risk materializes. This ensures that resources are available to manage and mitigate the impact of risks on the project, aligning with proactive risk management strategies in PRINCE2.

Reference: PRINCE2 7 Foundation Handbook and official training materials.