Which is a minimum requirement for applying the organization theme?

A.
To document the project management team structure
Answers
A.
To document the project management team structure
B.
To define the experience required for each project role
Answers
B.
To define the experience required for each project role
C.
To include external stakeholders on the project board
Answers
C.
To include external stakeholders on the project board
D.
To train project team members in the use of PRINCE2
Answers
D.
To train project team members in the use of PRINCE2
Suggested answer: A

Explanation:

A minimum requirement for applying the Organization Theme in PRINCE2 is to document the project management team structure. This documentation includes defining the roles and responsibilities of each team member, facilitating clear communication and effective management throughout the project lifecycle.

Reference: PRINCE2 7 Foundation Handbook and official training materials.