Question 1

Report Export Collapse

Which is a purpose of a Lessons Log?

Note any lessons that are raised in Checkpoint Reports
Note any lessons that are raised in Checkpoint Reports
Record that corrective action is being taken
Record that corrective action is being taken
Escalate lessons to the Project Board
Escalate lessons to the Project Board
Raise improvements with Project Assurance
Raise improvements with Project Assurance
Suggested answer: A
Explanation:

The purpose of a Lessons Log in PRINCE2 is to record all lessons that arise during the project, including those noted in Checkpoint Reports. This log helps in capturing valuable insights and learning points which can be used to improve future projects or later stages of the current project.

Reference: PRINCE2 Foundation official documentation and study materials.

asked 23/09/2024
Joice Lira
30 questions

Question 2

Report Export Collapse

Which is a true statement about PRINCE2 event-driven controls?

Event-driven controls take place at predefined periodic intervals
Event-driven controls take place at predefined periodic intervals
Event-driven controls are produced at the frequency defined in a Work Package
Event-driven controls are produced at the frequency defined in a Work Package
Event-driven controls are used for decision making
Event-driven controls are used for decision making
Checkpoint Reports are event-driven controls
Checkpoint Reports are event-driven controls
Suggested answer: C
Explanation:

PRINCE2 defines event-driven controls as those that are triggered by the occurrence of certain events within the project lifecycle, such as the completion of a product or phase. These controls are essential for decision-making because they provide necessary information at key points, allowing project managers and the Project Board to make informed decisions about the future of the project.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Michael Marzotto
36 questions

Question 3

Report Export Collapse

Why is it crucial that the Project Product Description clearly defines acceptance methods?

Enables Project Assurance to authorize quality activities
Enables Project Assurance to authorize quality activities
Defines how all project products will be reviewed and approved
Defines how all project products will be reviewed and approved
Defines how it will be proven that the completed project product meets the customer's expectations
Defines how it will be proven that the completed project product meets the customer's expectations
Provides confirmation that all project products have met their quality criteria
Provides confirmation that all project products have met their quality criteria
Suggested answer: C
Explanation:

The Project Product Description in PRINCE2 should clearly define acceptance methods to ensure that there is a concrete plan for demonstrating that the final project product meets the customer's quality expectations. This is crucial for aligning the project's outputs with the customer's needs and expectations. While it is part of broader quality control and assurance mechanisms, the specific role of defining acceptance methods is to make clear how compliance with quality expectations will be verified.

Reference: PRINCE2 7 Foundation study guide and documents.

asked 23/09/2024
Tuukka Valkeasuo
33 questions

Question 4

Report Export Collapse

Which is a purpose of the Quality theme?

Establish how the project will ensure that all products created meet their requirements
Establish how the project will ensure that all products created meet their requirements
Establish quality assurance to maintain the quality management system
Establish quality assurance to maintain the quality management system
Identify all the products of the project to ensure the scope has been adequately defined
Identify all the products of the project to ensure the scope has been adequately defined
Determine the communication needs of the organization's quality assurance function
Determine the communication needs of the organization's quality assurance function
Suggested answer: A
Explanation:

The primary purpose of the Quality theme in PRINCE2 is to establish and maintain the processes and procedures that will ensure all products created during the project meet the predefined quality requirements. This includes planning, assurance, and control of quality. The Quality theme focuses on defining and implementing quality standards that the project must adhere to, rather than dealing directly with broader organizational quality assurance or the project scope.

Reference: PRINCE2 7 Foundation handbook and other official documents.

asked 23/09/2024
Abid Ali Minhas
35 questions

Question 5

Report Export Collapse

Which statement defines a risk?

A certain event occurring in the future that will have a negative impact on the project's objectives
A certain event occurring in the future that will have a negative impact on the project's objectives
An event that has already occurred that the Project Manager must deal with immediately
An event that has already occurred that the Project Manager must deal with immediately
An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
Suggested answer: C
Explanation:

In PRINCE2, a risk is defined as any uncertain event or set of events that, if it occurs, will have an impact on the achievement of project objectives. This definition emphasizes the uncertainty and potential effect on objectives, rather than the certainty or immediate occurrence of an event.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Cyrom Meryll Santos
36 questions

Question 6

Report Export Collapse

Which risk response type is appropriate to respond to an opportunity?

Accept
Accept
Fallback
Fallback
Exploit
Exploit
Transfer
Transfer
Suggested answer: C
Explanation:

The risk response type 'Exploit' is specifically designed to ensure that the opportunity is realized. This response is proactive and aims at making changes to exploit the opportunity fully, which aligns with managing opportunities within PRINCE2 risk management.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Mike Schatens
31 questions

Question 7

Report Export Collapse

Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.

Avoid
Avoid
Reduce
Reduce
Share
Share
Transfer
Transfer
Suggested answer: D
Explanation:

The risk response type 'Transfer' is applicable to both threats and opportunities. This response involves transferring the ownership of the risk to a third party who is better able to manage the risk, thus applying to both positive and negative risks.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
David Stutz
31 questions

Question 8

Report Export Collapse

Which is NOT considered when defining risk tolerance?

A Project Board's attitude towards risk taking
A Project Board's attitude towards risk taking
The allocated risk budget
The allocated risk budget
An organization's risk appetite
An organization's risk appetite
The amount of risk a Project Board considers acceptable
The amount of risk a Project Board considers acceptable
Suggested answer: B
Explanation:

When defining risk tolerance, the factors considered include the Project Board's attitude towards risk, the organization's risk appetite, and the level of risk deemed acceptable by the Project Board. The allocated risk budget is not a direct consideration in defining risk tolerance; rather, it is a resource aspect managed within the tolerances set for the project.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Topic 2, Exam Pool B

asked 23/09/2024
Luis Antonio Sanchez Estrada
35 questions

Question 9

Report Export Collapse

Which is a purpose of an End Project Report?

Identify individuals or groups that need to be told that the project is coming to an end
Identify individuals or groups that need to be told that the project is coming to an end
Review how well the project performed against the Project Initiation Documentation used to authorize it
Review how well the project performed against the Project Initiation Documentation used to authorize it
Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
Ensure that key project information is archived and made secure
Ensure that key project information is archived and made secure
Suggested answer: B
Explanation:

The purpose of an End Project Report in PRINCE2 is to review how well the project performed against the Project Initiation Documentation (PID) used to authorize it. This report provides a final account of the project, including whether it met its objectives and delivered the expected benefits, and highlights lessons learned to inform future projects.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Miguel Bakker
30 questions

Question 10

Report Export Collapse

How many management stages should a PRINCE2 project consist of?

Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
Initiation stage and at least one other management stage to cover the remainder of the project
Initiation stage and at least one other management stage to cover the remainder of the project
Start up stage, initiation stage and a closing stage
Start up stage, initiation stage and a closing stage
Suggested answer: A
Explanation:

A PRINCE2 project should consist of a start-up stage, an initiation stage, and at least one other management stage to cover the remainder of the project. This structure ensures that the project is properly initiated and planned before entering into a series of management stages where the work is executed and completed, followed by a closing stage.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Mark Lalangan
38 questions
Total 463 questions