PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers
List of questions
Related questions
Question 1
Which is a purpose of a Lessons Log?
Explanation:
The purpose of a Lessons Log in PRINCE2 is to record all lessons that arise during the project, including those noted in Checkpoint Reports. This log helps in capturing valuable insights and learning points which can be used to improve future projects or later stages of the current project.
Reference: PRINCE2 Foundation official documentation and study materials.
Question 2
Which is a true statement about PRINCE2 event-driven controls?
Explanation:
PRINCE2 defines event-driven controls as those that are triggered by the occurrence of certain events within the project lifecycle, such as the completion of a product or phase. These controls are essential for decision-making because they provide necessary information at key points, allowing project managers and the Project Board to make informed decisions about the future of the project.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 3
Why is it crucial that the Project Product Description clearly defines acceptance methods?
Explanation:
The Project Product Description in PRINCE2 should clearly define acceptance methods to ensure that there is a concrete plan for demonstrating that the final project product meets the customer's quality expectations. This is crucial for aligning the project's outputs with the customer's needs and expectations. While it is part of broader quality control and assurance mechanisms, the specific role of defining acceptance methods is to make clear how compliance with quality expectations will be verified.
Reference: PRINCE2 7 Foundation study guide and documents.
Question 4
Which is a purpose of the Quality theme?
Explanation:
The primary purpose of the Quality theme in PRINCE2 is to establish and maintain the processes and procedures that will ensure all products created during the project meet the predefined quality requirements. This includes planning, assurance, and control of quality. The Quality theme focuses on defining and implementing quality standards that the project must adhere to, rather than dealing directly with broader organizational quality assurance or the project scope.
Reference: PRINCE2 7 Foundation handbook and other official documents.
Question 5
Which statement defines a risk?
Explanation:
In PRINCE2, a risk is defined as any uncertain event or set of events that, if it occurs, will have an impact on the achievement of project objectives. This definition emphasizes the uncertainty and potential effect on objectives, rather than the certainty or immediate occurrence of an event.
Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.
Question 6
Which risk response type is appropriate to respond to an opportunity?
Explanation:
The risk response type 'Exploit' is specifically designed to ensure that the opportunity is realized. This response is proactive and aims at making changes to exploit the opportunity fully, which aligns with managing opportunities within PRINCE2 risk management.
Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.
Question 7
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.
Explanation:
The risk response type 'Transfer' is applicable to both threats and opportunities. This response involves transferring the ownership of the risk to a third party who is better able to manage the risk, thus applying to both positive and negative risks.
Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.
Question 8
Which is NOT considered when defining risk tolerance?
Explanation:
When defining risk tolerance, the factors considered include the Project Board's attitude towards risk, the organization's risk appetite, and the level of risk deemed acceptable by the Project Board. The allocated risk budget is not a direct consideration in defining risk tolerance; rather, it is a resource aspect managed within the tolerances set for the project.
Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.
Topic 2, Exam Pool B
Question 9
Which is a purpose of an End Project Report?
Explanation:
The purpose of an End Project Report in PRINCE2 is to review how well the project performed against the Project Initiation Documentation (PID) used to authorize it. This report provides a final account of the project, including whether it met its objectives and delivered the expected benefits, and highlights lessons learned to inform future projects.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question 10
How many management stages should a PRINCE2 project consist of?
Explanation:
A PRINCE2 project should consist of a start-up stage, an initiation stage, and at least one other management stage to cover the remainder of the project. This structure ensures that the project is properly initiated and planned before entering into a series of management stages where the work is executed and completed, followed by a closing stage.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources
Question