Where should decisions regarding the tailoring of the project be recorded?

A.
Project brief
A.
Project brief
Answers
B.
Project initiation documentation
B.
Project initiation documentation
Answers
C.
Project mandate
C.
Project mandate
Answers
D.
Stage plan
D.
Stage plan
Answers
Suggested answer: B

Explanation:

Decisions regarding the tailoring of the project should be recorded in the Project Initiation Documentation (PID). The PID is the key document that defines how the project is to be managed and includes specific references to any tailoring decisions made to fit the project's environment.

Reference: PRINCE2 Foundation Handbook, Project Initiation Documentation section.

Which describes an off-specification?

A.
An interdependency between products that was previously unidentified
A.
An interdependency between products that was previously unidentified
Answers
B.
The addition of an improvement to a product description
B.
The addition of an improvement to a product description
Answers
C.
A prototype demonstrating a possible design solution
C.
A prototype demonstrating a possible design solution
Answers
D.
The production of more than the defined quantity of a specialist product
D.
The production of more than the defined quantity of a specialist product
Answers
Suggested answer: D

Explanation:

An off-specification in PRINCE2 is a situation where a planned product does not meet its quality criteria or other requirements specified in the product description. This could include producing more or less than the defined quantity, implying deviation from the agreed specifications.

Reference: PRINCE2 Foundation Handbook, Off-Specifications section.

Which process monitors work that has been assigned to a team manager?

A.
Controlling a stage
A.
Controlling a stage
Answers
B.
Directing a project
B.
Directing a project
Answers
C.
Managing a stage boundary
C.
Managing a stage boundary
Answers
D.
Managing product delivery
D.
Managing product delivery
Answers
Suggested answer: D

Explanation:

The 'Managing Product Delivery' process in PRINCE2 is designed to monitor the work assigned to a team manager. This process ensures that the work is completed according to the specifications agreed upon in the Work Package and provides a mechanism for the team manager to report progress back to the project manager.

Reference: PRINCE2 Foundation Handbook, Managing Product Delivery section.

Which is a minimum requirement for applying the quality theme?

A.
Appraisal methods of quality control must be carried out on products
A.
Appraisal methods of quality control must be carried out on products
Answers
B.
A record must be kept of all the quality management activities that are planned
B.
A record must be kept of all the quality management activities that are planned
Answers
C.
The quality review technique must be used when reviewing products
C.
The quality review technique must be used when reviewing products
Answers
D.
The quality management approach must align with corporate standards
D.
The quality management approach must align with corporate standards
Answers
Suggested answer: B

Explanation:

A minimum requirement for applying the quality theme in PRINCE2 is keeping a record of all planned quality management activities. This requirement ensures that there is clear documentation of what quality checks will occur, who will perform them, and how they will be executed, which is fundamental for maintaining control over quality assurance throughout the project.

Reference: PRINCE2 Foundation Handbook, Quality Theme section.

Which approach must be followed as a minimum requirement for applying the plans theme?

A.
Activity-based planning
A.
Activity-based planning
Answers
B.
Product-based planning
B.
Product-based planning
Answers
C.
Agile
C.
Agile
Answers
D.
Risk management
D.
Risk management
Answers
Suggested answer: B

Explanation:

The minimum requirement for applying the Plans Theme in PRINCE2 is following the product-based planning approach. This approach involves creating a product breakdown structure, writing product descriptions, and defining product dependencies before developing the schedule and resource plans. It ensures that plans are focused on the project's deliverables and their quality requirements.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Identify the missing words in the following sentence.

The project manager [ ? ] for day-to-day management of the project.

A.
and the project board are responsible
A.
and the project board are responsible
Answers
B.
and the team manager(s) are accountable
B.
and the team manager(s) are accountable
Answers
C.
has responsibility
C.
has responsibility
Answers
D.
decides who is responsible
D.
decides who is responsible
Answers
Suggested answer: C

Explanation:

The correct phrase that completes the sentence is 'The project manager has responsibility for day-to-day management of the project.' This highlights the project manager's role in overseeing the project's daily operations, ensuring that project activities align with the overall plan and objectives.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

What may be funded from a risk budget?

A.
Corrections required due to off-specifications
A.
Corrections required due to off-specifications
Answers
B.
Impact analysis of requests for change
B.
Impact analysis of requests for change
Answers
C.
Implementation of a fallback plan
C.
Implementation of a fallback plan
Answers
D.
Preparation of the risk management approach
D.
Preparation of the risk management approach
Answers
Suggested answer: C

Explanation:

A risk budget may fund the implementation of a fallback plan, which is activated if a risk materializes. This ensures that resources are available to manage and mitigate the impact of risks on the project, aligning with proactive risk management strategies in PRINCE2.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which is a minimum requirement for applying the organization theme?

A.
To document the project management team structure
A.
To document the project management team structure
Answers
B.
To define the experience required for each project role
B.
To define the experience required for each project role
Answers
C.
To include external stakeholders on the project board
C.
To include external stakeholders on the project board
Answers
D.
To train project team members in the use of PRINCE2
D.
To train project team members in the use of PRINCE2
Answers
Suggested answer: A

Explanation:

A minimum requirement for applying the Organization Theme in PRINCE2 is to document the project management team structure. This documentation includes defining the roles and responsibilities of each team member, facilitating clear communication and effective management throughout the project lifecycle.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Who represents the three project interests on a project?

A.
Project manager
A.
Project manager
Answers
B.
Project support
B.
Project support
Answers
C.
External project stakeholders
C.
External project stakeholders
Answers
D.
Project board
D.
Project board
Answers
Suggested answer: D

Explanation:

The project board in PRINCE2 represents the three project interests, which are business (value for money), user (those who will use the project's outputs), and supplier (those who provide the resources and skills). The project board is responsible for overseeing the project, ensuring that it delivers value and meets the requirements set out by these three interest groups.

Reference: PRINCE2 Foundation Handbook, Project Board section.

Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?

A.
Defined roles and responsibilities
A.
Defined roles and responsibilities
Answers
B.
Learn from experience
B.
Learn from experience
Answers
C.
Manage by exception
C.
Manage by exception
Answers
D.
Focus on products
D.
Focus on products
Answers
Suggested answer: B

Explanation:

The PRINCE2 principle of 'Learn from experience' addresses concerns about the project team's familiarity with similar projects. It mandates that project teams seek out and learn from previous relevant experiences and lessons logged in prior projects to enhance their effectiveness and efficiency, even when facing unfamiliar project scenarios.

Reference: PRINCE2 Foundation Handbook, Learn from Experience principle section.