What must a PRINCE2 project demonstrate?

A.
Application of PRINCE2 principles
A.
Application of PRINCE2 principles
Answers
B.
Application of proper leadership skills
B.
Application of proper leadership skills
Answers
C.
Application of the activities in each process
C.
Application of the activities in each process
Answers
D.
Application of tools appropriate for the industry
D.
Application of tools appropriate for the industry
Answers
Suggested answer: A

Explanation:

A PRINCE2 project must demonstrate the application of its seven principles throughout the project's lifecycle. These principles are universal, self-validating, and empowering, ensuring that the project management approach is effective and applicable under various project circumstances.

Reference: PRINCE2 Foundation Handbook, Principles section.

=========================

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

A.
corporate, programme management or the customer
A.
corporate, programme management or the customer
Answers
B.
the project board
B.
the project board
Answers
C.
the project manager
C.
the project manager
Answers
D.
the change authority
D.
the change authority
Answers
Suggested answer: B

Explanation:

PRINCE2 requires that the business case be formally verified by the project board at stage boundaries. This verification is essential to ensure that the project remains viable and desirable from a business perspective. The project board's review of the business case at these critical points helps in deciding whether the project should continue into its next stage.

Reference: PRINCE2 Foundation Manual

What process provides information on a team's work to the project manager?

A.
Controlling a stage
A.
Controlling a stage
Answers
B.
Directing a project
B.
Directing a project
Answers
C.
Managing a stage boundary
C.
Managing a stage boundary
Answers
D.
Managing product delivery
D.
Managing product delivery
Answers
Suggested answer: D

Explanation:

The process that provides information on a team's work to the project manager in PRINCE2 is 'Managing Product Delivery'. This process involves the management of the link between the project manager and the team members, through which the team manager reports the progress of work packages to the project manager, ensuring that work is being completed as planned and that any issues are communicated.

Reference: PRINCE2 Foundation Manual

According to the 'defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?

A.
One
A.
One
Answers
B.
Two
B.
Two
Answers
C.
Three
C.
Three
Answers
D.
Six
D.
Six
Answers
Suggested answer: C

Explanation:

According to the 'defined roles and responsibilities' principle in PRINCE2, three categories of stakeholder interest need to be represented in the project management team: business (represented by the Executive), user (represented by the Senior User), and supplier (represented by the Senior Supplier). This ensures that the key perspectives on the project's outputs, outcomes, and processes are fully integrated into decision-making and governance structures.

Reference: PRINCE2 Foundation ManualAccording to the 'defined roles and responsibilities' principle in PRINCE2, three categories of stakeholder interest need to be represented in the project management team: business (represented by the Executive), user (represented by the Senior User), and supplier (represented by the Senior Supplier). This ensures that the key perspectives on the project's outputs, outcomes, and processes are fully integrated into decision-making and governance structures. Reference: PRINCE2 Foundation Manual

Which is a purpose of a quality register?

A.
To record cross-references to issues relating to the quality of the products
A.
To record cross-references to issues relating to the quality of the products
Answers
B.
To record the date a completed work package was received
B.
To record the date a completed work package was received
Answers
C.
To provide the status of quality activities carried out for completed products
C.
To provide the status of quality activities carried out for completed products
Answers
D.
To capture quality concerns about completed products
D.
To capture quality concerns about completed products
Answers
Suggested answer: C

Explanation:

The purpose of a Quality Register in PRINCE2 is to provide a detailed record of all quality activities that are planned and carried out over the course of the project. It includes information such as who will perform the quality check, what standards must be met, and the status and outcome of these quality activities. This ensures that each product meets its defined quality criteria before being deemed complete.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which is an objective of the 'directing a project' process?

A.
To tailor the project's products and roles so that the project suits the circumstances
A.
To tailor the project's products and roles so that the project suits the circumstances
Answers
B.
To respond to the project mandate by starting up a project
B.
To respond to the project mandate by starting up a project
Answers
C.
To provide an interface between the project and corporate management
C.
To provide an interface between the project and corporate management
Answers
D.
To ensure the stage products are delivered to the stated quality standards
D.
To ensure the stage products are delivered to the stated quality standards
Answers
Suggested answer: C

Explanation:

An objective of the 'Directing a Project' process in PRINCE2 is to provide an interface between the project management and the wider corporate, programme management, or customer environment. This process ensures that the project remains aligned with the organization's objectives and governance frameworks, and that corporate or programme management can provide oversight and support as needed.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which is a minimum requirement for applying the quality theme?

A.
To define the project's approach to quality assurance
A.
To define the project's approach to quality assurance
Answers
B.
To appoint external reviewers for quality reviews
B.
To appoint external reviewers for quality reviews
Answers
C.
To define quality criteria in product descriptions
C.
To define quality criteria in product descriptions
Answers
D.
To provide administrative support for quality controls
D.
To provide administrative support for quality controls
Answers
Suggested answer: C

Explanation:

A minimum requirement for applying the quality theme in PRINCE2 is to define quality criteria within product descriptions. This includes specifying what the product must do, the standards it must meet, and how quality will be evaluated, ensuring that all project products deliver against the agreed-upon requirements and standards.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which statement about the length of management stages in a project is CORRECT?

A.
A higher level of major risk will require a stage to be longer
A.
A higher level of major risk will require a stage to be longer
Answers
B.
Stage length is influenced by project board availability
B.
Stage length is influenced by project board availability
Answers
C.
A higher level of major risk will require a stage to be shorter
C.
A higher level of major risk will require a stage to be shorter
Answers
D.
Use of management stages represents a time driven control
D.
Use of management stages represents a time driven control
Answers
Suggested answer: B

Explanation:

The length of management stages in a PRINCE2 project can be influenced by the availability of the project board to review and approve key decisions at stage boundaries. This ensures that stages are planned around when decision-makers can participate and provide necessary guidance or approvals.

Reference: = PRINCE2 7 Foundation handbook and online resources

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: B

Explanation:

A risk budget should be used to implement contingency plans (2) and actions to avoid a risk from occurring (3). This budget is set aside to fund specific actions that are part of the project's risk management strategy, enabling proactive and reactive responses to identified risks, ensuring the project remains on track despite uncertainties.

Reference: = PRINCE2 7 Foundation handbook and online resources

According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?

A.
Project board, project manager and project assurance roles
A.
Project board, project manager and project assurance roles
Answers
B.
Directing, managing and delivering levels
B.
Directing, managing and delivering levels
Answers
C.
Business, user and supplier interests
C.
Business, user and supplier interests
Answers
D.
Corporate, programme management or the customer parties
D.
Corporate, programme management or the customer parties
Answers
Suggested answer: C

Explanation:

According to the 'defined roles and responsibilities' principle in PRINCE2, the project management team must represent the business, user, and supplier interests. This ensures that all critical viewpoints are considered in decision-making processes, aligning the project outcomes closely with organizational needs and stakeholder expectations.

Reference: PRINCE2 Foundation Handbook, Defined Roles and Responsibilities section.