PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 27
List of questions
Question 261
Which is a minimum requirement for applying the risk theme?
Question 262
According to PRINCE2, which characteristic is necessary for an effective project board?
Question 263
Which is an objective of the 'directing a project' process?
Question 264
Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?
Question 265
Which product defines how the project board should approve the management products produced during the 'initiating a project' process?
Question 266
Which product describes the method the project will use to engage with corporate, programme management or the customer?
Question 267
Which is one of the six aspects of project performance to be managed?
Question 268
Which is a purpose of the business case theme?
Question 269
Which role is responsible for appointing the senior user in a project that is independent from a program?
Question 270
What is a goal of the 'implement' step within the recommended risk management procedure?
Question