ExamGecko
Home Home / PRINCE2 / PRINCE2-7-Foundation

PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 27

Question list
Search
Search

Which is a minimum requirement for applying the risk theme?

A.
Threats must be assessed for their impact on the viability of the project
A.
Threats must be assessed for their impact on the viability of the project
Answers
B.
A single role that is responsible for all risks must be defined
B.
A single role that is responsible for all risks must be defined
Answers
C.
The PRINCE2 risk management procedure must be followed
C.
The PRINCE2 risk management procedure must be followed
Answers
D.
Team managers must maintain their own risk registers
D.
Team managers must maintain their own risk registers
Answers
Suggested answer: C

Explanation:

A minimum requirement for applying the Risk Theme in PRINCE2 is to follow the PRINCE2 risk management procedure. This procedure includes the systematic process of identifying, assessing, and controlling project risks, ensuring that risks are managed proactively throughout the project.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

According to PRINCE2, which characteristic is necessary for an effective project board?

A.
An ability to delegate
A.
An ability to delegate
Answers
B.
An attention to detail
B.
An attention to detail
Answers
C.
A calm management style
C.
A calm management style
Answers
D.
A 'problem-solving' approach
D.
A 'problem-solving' approach
Answers
Suggested answer: A

Explanation:

According to PRINCE2, an effective project board must have the ability to delegate appropriately. This characteristic is essential to ensure that decisions and tasks are assigned to the right members of the project management team, facilitating efficient governance and management of the project.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which is an objective of the 'directing a project' process?

A.
To review and approve a project mandate
A.
To review and approve a project mandate
Answers
B.
To ensure corporate or programme management has an interface to the project
B.
To ensure corporate or programme management has an interface to the project
Answers
C.
To define how risks, issues and changes will be managed
C.
To define how risks, issues and changes will be managed
Answers
D.
To obtain approval for completed products
D.
To obtain approval for completed products
Answers
Suggested answer: B

Explanation:

One of the objectives of the 'Directing a Project' process in PRINCE2 is to ensure that there is a clear interface between the project and corporate or programme management. This process enables strategic oversight and decision-making, aligning the project with broader organizational objectives and governance frameworks.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

A.
To identify responses to risks documented in the business case
A.
To identify responses to risks documented in the business case
Answers
B.
To identify information about the project environment and objectives
B.
To identify information about the project environment and objectives
Answers
C.
To identify the roles to be involved in risk management activities
C.
To identify the roles to be involved in risk management activities
Answers
D.
To identify uncertainties that may impact on the delivery of the project objectives
D.
To identify uncertainties that may impact on the delivery of the project objectives
Answers
Suggested answer: D

Explanation:

The purpose of the 'Identify the Risks' step within the recommended risk management procedure is to identify uncertainties that may impact the achievement of project objectives. This step involves recognizing potential issues and challenges that could threaten the project's success, enabling proactive management and mitigation strategies.

Reference: PRINCE2 7 Foundation Handbook and official training materials.

Which product defines how the project board should approve the management products produced during the 'initiating a project' process?

A.
Communication management approach
A.
Communication management approach
Answers
B.
Quality management approach
B.
Quality management approach
Answers
C.
Project plan
C.
Project plan
Answers
D.
Initiation stage plan
D.
Initiation stage plan
Answers
Suggested answer: D

Explanation:

The Initiation Stage Plan specifies how the project board should approve management products produced during the 'initiating a project' process. It sets out the plan for the initiation stage, detailing the management and control of this stage, including how deliverables are to be reviewed and approved.

Reference: PRINCE2 7 Foundation Source: PRINCE2 Foundation handbook and online resources

Which product describes the method the project will use to engage with corporate, programme management or the customer?

A.
Quality management approach
A.
Quality management approach
Answers
B.
Communication management approach
B.
Communication management approach
Answers
C.
Change control approach
C.
Change control approach
Answers
D.
Benefits management approach
D.
Benefits management approach
Answers
Suggested answer: B

Explanation:

The Communication Management Approach describes the means and frequency of communication to parties both within and outside the project. It outlines how the project will engage with stakeholders, including corporate, programme management, or the customer. This approach ensures that necessary information is provided to the right stakeholders at the right time.

Reference: PRINCE2 7 Foundation Source: PRINCE2 Foundation handbook and online resources

Which is one of the six aspects of project performance to be managed?

A.
Efficiency
A.
Efficiency
Answers
B.
Timescales
B.
Timescales
Answers
C.
Estimate
C.
Estimate
Answers
D.
Work
D.
Work
Answers
Suggested answer: B

Explanation:

One of the six aspects of project performance to be managed according to PRINCE2 is 'timescales'. Managing timescales involves planning and controlling when products will be delivered and ensuring the project remains within the agreed schedule.

Reference: PRINCE2 7 Foundation Source: PRINCE2 Foundation handbook and online resources

Which is a purpose of the business case theme?

A.
To identify which role is responsible for producing the business case
A.
To identify which role is responsible for producing the business case
Answers
B.
To identify the project's outputs
B.
To identify the project's outputs
Answers
C.
To establish the controls to manage changes that may impact the project benefits
C.
To establish the controls to manage changes that may impact the project benefits
Answers
D.
To establish a viable investment proposition
D.
To establish a viable investment proposition
Answers
Suggested answer: D

Explanation:

The purpose of the Business Case theme in PRINCE2 is to establish a viable investment proposition. It justifies the investment in the project through an ongoing assessment of benefits, costs, and risks, ensuring that the project remains desirable, viable, and achievable throughout its life.

Reference: PRINCE2 7 Foundation Source: PRINCE2 Foundation handbook and online resources

Which role is responsible for appointing the senior user in a project that is independent from a program?

A.
The project manager
A.
The project manager
Answers
B.
The executive
B.
The executive
Answers
C.
Corporate, program management or the customer
C.
Corporate, program management or the customer
Answers
D.
Project assurance
D.
Project assurance
Answers
Suggested answer: C

Explanation:

In PRINCE2, the role responsible for appointing the Senior User, as well as other key project roles such as the Executive and the Senior Supplier, is typically taken by someone from corporate or program management, or the customer. This aligns with the principle of clearly defined roles and responsibilities, ensuring that the project has clear governance and accountability. The Senior User is appointed to represent the interests of all those who will use the project's products, who will benefit from the outcomes, and those whose work might be impacted by the change.

Reference: PRINCE2 Foundation Manual

What is a goal of the 'implement' step within the recommended risk management procedure?

A.
To prepare specific management responses to identified risks
A.
To prepare specific management responses to identified risks
Answers
B.
To monitor the effectiveness of actioned risk responses
B.
To monitor the effectiveness of actioned risk responses
Answers
C.
To estimate the risk to the project in terms of probability and impact
C.
To estimate the risk to the project in terms of probability and impact
Answers
D.
To communicate information related to the risks faced by the project
D.
To communicate information related to the risks faced by the project
Answers
Suggested answer: A

Explanation:

The goal of the 'implement' step within the recommended risk management procedure in PRINCE2 is to prepare specific management responses to the identified risks. This involves developing strategies to enhance opportunities and reduce threats to the project's objectives, ensuring that appropriate responses are ready for implementation.

Reference: = PRINCE2 7 Foundation handbook and online resources

Total 463 questions
Go to page: of 47