The senior user needs to understand how user assurance will support the senior user on the project.
Which management product should the senior user review?
A.
Project plan
B.
Project management team structure
C.
Role descriptions
D.
Project log
Thea project manager needs to report to the project board on the status of the project's issues.
Which management product should the project manager review?
A.
Project log
B.
Project brief
C.
Checkpoint report
D.
Highlight report
Identify the missing word in the following sentence.
is the measurable decline resulting from a negative outcome?
A.
An exception
B.
A dis-benefit
C.
An off-specification
D.
A risk