What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

A.
Benefits sustainability
A.
Benefits sustainability
Answers
B.
Product sustainability
B.
Product sustainability
Answers
C.
Delivery sustainability
C.
Delivery sustainability
Answers
D.
Quality sustainability
D.
Quality sustainability
Answers
Suggested answer: A

Explanation:

When a project manager plans to keep the CO2 emissions of the project aligned with the business strategy, this addresses 'benefits sustainability'. This aspect involves ensuring that the project's outcomes and benefits are sustainable and align with broader business strategies, such as environmental objectives and corporate responsibility goals.

Reference: PRINCE2 7 Foundation documentation on sustainability in project management.

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

A.
Initiating a project
A.
Initiating a project
Answers
B.
Starting up a project
B.
Starting up a project
Answers
C.
Controlling a stage
C.
Controlling a stage
Answers
D.
Managing product delivery
D.
Managing product delivery
Answers
Suggested answer: D

Explanation:

The 'managing product delivery' process in PRINCE2 defines the work needed to deliver major products, ensuring effective use of organizational resources. This process focuses on the acceptance, execution, and delivery of project products according to agreed plans between the project manager and the team manager.

Reference: PRINCE2 7 Foundation guide on the 'managing product delivery' process.

===========

The project board needs to review whether the investment remains justified as the project progresses according to plan.

Which principle is being applied by the 'business case' practice when the project board undertakes this review?

A.
Manage by exception
A.
Manage by exception
Answers
B.
Manage by stages
B.
Manage by stages
Answers
C.
Focus on products
C.
Focus on products
Answers
D.
Tailor to suit the project
D.
Tailor to suit the project
Answers
Suggested answer: B

Explanation:

When the project board reviews whether the investment remains justified as the project progresses, this application of the 'manage by stages' principle is evident. This principle ensures that at the end of each stage, the project board reassesses the business case and the viability of the project before deciding to continue with the next stage.

Reference: PRINCE2 7 Foundation resources on the 'manage by stages' principle.

The project manager needs to understand what makes the outputs acceptable to the users.

In which step of the 'planning' technique should this occur?

A.
Defining and analysing the products
A.
Defining and analysing the products
Answers
B.
Organizing work packages
B.
Organizing work packages
Answers
C.
Preparing estimates
C.
Preparing estimates
Answers
D.
Preparing a schedule
D.
Preparing a schedule
Answers
Suggested answer: A

Explanation:

In the 'planning' technique of PRINCE2, understanding what makes the outputs acceptable to the users occurs during the step of 'Defining and Analyzing the Products.' This step involves detailed discussions about product requirements and specifications to ensure clarity on what the project must deliver for it to be accepted by the users. It sets out the criteria that the products must meet to satisfy the user's needs and expectations.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

The team manager has organized a workshop with project stakeholders to define the detailed requirements for a number of outputs.

Which principle is being applied by the team manager as part of the 'people' element when holding this workshop?

A.
Focus on products
A.
Focus on products
Answers
B.
Tailor to suit the project
B.
Tailor to suit the project
Answers
C.
Define roles, responsibilities and relationships
C.
Define roles, responsibilities and relationships
Answers
D.
Ensure continued business justification
D.
Ensure continued business justification
Answers
Suggested answer: A

Explanation:

By organizing a workshop with project stakeholders to define the detailed requirements for project outputs, the team manager is applying the PRINCE2 principle of 'Focus on Products.' This principle emphasizes that a project's primary focus should be on product definition, delivery, and quality requirements, which are crucial for achieving project success and user satisfaction.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

Which is an internal factor to consider when tailoring PRINCE??

A.
The safety legislation
A.
The safety legislation
Answers
B.
The environmental standards
B.
The environmental standards
Answers
C.
The industry's regulations
C.
The industry's regulations
Answers
D.
The organization's procedures
D.
The organization's procedures
Answers
Suggested answer: D

Explanation:

An internal factor to consider when tailoring PRINCE2 to a specific project environment is 'The organization's procedures.' Tailoring must take into account internal practices, procedures, and organizational culture to ensure that the project management approach aligns well with internal governance and can be effectively integrated within the organizational context.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

What should the 'organizing' practice address?

A.
How to meet the user's requirements of the project products
A.
How to meet the user's requirements of the project products
Answers
B.
Which members of the project management team should report to whom
B.
Which members of the project management team should report to whom
Answers
C.
What might go wrong that could affect the achievement of the business objectives
C.
What might go wrong that could affect the achievement of the business objectives
Answers
D.
who will be impacted by the change and how they will need to transition the new capabilities
D.
who will be impacted by the change and how they will need to transition the new capabilities
Answers
Suggested answer: B

Explanation:

The 'organizing' practice in PRINCE2 should address how the project management team is structured, specifically detailing which team members should report to whom. This practice ensures clear lines of communication and responsibility within the project team, facilitating effective management and decision-making processes.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

The project manager is acting as the team manager and needs to control the work of a team member who reports to them.

Which management product should the project manager use to control this work?

A.
A work package description
A.
A work package description
Answers
B.
The project management team structure
B.
The project management team structure
Answers
C.
A stage plan
C.
A stage plan
Answers
D.
A work breakdown structure
D.
A work breakdown structure
Answers
Suggested answer: A

Explanation:

When the project manager is also acting as the team manager, they should use a 'Work Package Description' to control the work of a team member. This management product details what is to be delivered, the reporting requirements, and the tolerances within which the team member must work, providing a clear definition and control mechanism for delegated tasks.

Reference: PRINCE2 7 Foundation guide on management products, specifically Work Packages.

Which statement about the 'manage by stages' principle is CORRECT?

A.
The project board should authorize multiple stages at the same time
A.
The project board should authorize multiple stages at the same time
Answers
B.
The end of a stage should provide a control point for the project board
B.
The end of a stage should provide a control point for the project board
Answers
C.
A project should have fewer, longer stages when the risk exposure is high
C.
A project should have fewer, longer stages when the risk exposure is high
Answers
D.
A project should have separate stages to plan, deliver and close the project
D.
A project should have separate stages to plan, deliver and close the project
Answers
Suggested answer: B

Explanation:

The 'manage by stages' principle in PRINCE2 dictates that the end of each stage provides a control point at which the project board can review progress, reassess project viability, and decide on the next steps. This approach allows for regular monitoring and decision-making, ensuring that the project remains aligned with its objectives and within its tolerances.

Reference: PRINCE2 7 Foundation guide on the 'manage by stages' principle.

Which common project context relates to the need to engage with external suppliers to deliver part of the project?

A.
Commercial
A.
Commercial
Answers
B.
Delivery method
B.
Delivery method
Answers
C.
Organizational
C.
Organizational
Answers
D.
Scale
D.
Scale
Answers
Suggested answer: A

Explanation:

The need to engage with external suppliers for delivering parts of the project is commonly related to the 'Commercial' project context in PRINCE2. This context involves considerations around contractual arrangements, procurement, and the management of supplier relationships which are crucial for projects relying on external vendors for key components or services.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)