Which is a definition of management?

A.
Directing the execution of project tasks as agreed for the project
A.
Directing the execution of project tasks as agreed for the project
Answers
B.
Away of working that characterises a group of people
B.
Away of working that characterises a group of people
Answers
C.
Being accountable to the business for the success of the project
C.
Being accountable to the business for the success of the project
Answers
D.
The party responsible for commissioning the project
D.
The party responsible for commissioning the project
Answers
Suggested answer: A

Explanation:

The definition of management in the context of PRINCE2 involves directing the execution of project tasks as agreed for the project. Management encompasses the actions and decisions necessary to ensure that the project's tasks are completed as planned, aligning with the agreed methods and standards.

Reference: PRINCE2 7 Foundation resources on project management principles.

According to the 'manage by exception' principle, which aspect of performance sets limits against the cost of aggregated threats?

A.
Risk
A.
Risk
Answers
B.
Scope
B.
Scope
Answers
C.
Quality
C.
Quality
Answers
D.
Cost
D.
Cost
Answers
Suggested answer: D

Explanation:

The principle of 'manage by exception' in PRINCE2 involves setting limits on delegated authority concerning time, cost, quality, scope, risk, and benefits. Here, the aspect of performance that sets limits against the cost of aggregated threats is 'Cost'. This includes setting tolerances for what can be considered acceptable deviations from the plan before an issue needs to be escalated to a higher authority. Managing by exception helps in efficient use of management time and focuses on deviations that might affect the project's success.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

What is a description of a leadership activity within a project?

A.
Understanding and working with different departments outside of the project team
A.
Understanding and working with different departments outside of the project team
Answers
B.
Agreeing a work package with a team manager to deliver products using specific tools
B.
Agreeing a work package with a team manager to deliver products using specific tools
Answers
C.
Ensuring that a co-located project team uses the agreed communication methods
C.
Ensuring that a co-located project team uses the agreed communication methods
Answers
D.
Creating a stage plan and product descriptions for the products to be created in the next stage
D.
Creating a stage plan and product descriptions for the products to be created in the next stage
Answers
Suggested answer: B

Explanation:

A leadership activity within a PRINCE2 project involves several responsibilities, one of which is agreeing on work packages with team managers. This agreement includes specifying the tools and techniques to be used for product delivery. This activity is crucial for ensuring clarity and mutual understanding of how work is to be conducted, facilitating effective delegation and accountability within the project team.

Reference: (PRINCE2 7 Foundation Study Guide, AXELOS)

The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?

A.
The business objectives
A.
The business objectives
Answers
B.
The business' existing governance practices
B.
The business' existing governance practices
Answers
C.
The project's delivery method
C.
The project's delivery method
Answers
D.
The ways of working used on previous projects
D.
The ways of working used on previous projects
Answers
Suggested answer: A

Explanation:

hen the project board reviews the Project Initiation Documentation (PID), it is essential to ensure that the PID is aligned with the business objectives. The PID should encapsulate the project's definition, including the reasons for undertaking the project, the benefits expected, and how it aligns with the broader business goals. Ensuring this alignment helps validate that the project remains viable and worthwhile as it progresses.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

How should effective issue management be applied When changing management products?

A.
By changing the issue management approach at the end of each stage to reflect lessons
A.
By changing the issue management approach at the end of each stage to reflect lessons
Answers
B.
By creating new versions of a management product when a change is approved
B.
By creating new versions of a management product when a change is approved
Answers
C.
By Implementing a change budget to fund changes to the project product
C.
By Implementing a change budget to fund changes to the project product
Answers
D.
By recording the required change to a management product as an off-specification
D.
By recording the required change to a management product as an off-specification
Answers
Suggested answer: B

Explanation:

Effective issue management in PRINCE2 should involve creating new versions of management products whenever a change is approved. This practice ensures that all documentation reflects the most current understanding and agreements regarding the project's scope and requirements. It helps maintain the integrity and relevance of the project documentation throughout its lifecycle, facilitating effective governance and control.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

In which step of the Issue management' technique should Superseded versions be archives?

A.
Implementing changes
A.
Implementing changes
Answers
B.
Assessing issues
B.
Assessing issues
Answers
C.
capturing issues
C.
capturing issues
Answers
D.
Deciding on changes
D.
Deciding on changes
Answers
Suggested answer: D

Explanation:

In PRINCE2, the 'Issue and Change Control' procedure encompasses the management of issues throughout the project lifecycle, including capturing, examining, and deciding on issues. Archiving superseded versions is part of the final step in the 'Deciding on changes' phase, where decisions are made on the issues and subsequent actions, including updates to project baselines and documentation, are implemented and archived as necessary.

Reference: PRINCE2 7 Foundation handbook and official resources on issue management technique.

As part of the 'business case management' technique, how is the business case maintained during the project lifecycle?

A.
By linking the outcomes and benefits to the business objectives included in the business case
A.
By linking the outcomes and benefits to the business objectives included in the business case
Answers
B.
By updating the business case during each management stage, as actual costs are incurred
B.
By updating the business case during each management stage, as actual costs are incurred
Answers
C.
By providing a robust justification for the entire project in a detailed business case
C.
By providing a robust justification for the entire project in a detailed business case
Answers
D.
By justifying to the project board that the project should be initiated
D.
By justifying to the project board that the project should be initiated
Answers
Suggested answer: B

Explanation:

Maintaining the business case during the project lifecycle involves regularly updating it to reflect changes and actual experiences such as incurred costs. This ensures that the project remains viable and aligned with business objectives, as part of the continual justification process. The business case is dynamically managed to reflect any changes in the project's environment and is a fundamental part of the 'business case theme' in PRINCE2.

Reference: PRINCE2 7 Foundation source documents on business case management.

Which action contributes to achieving the 'ensure continued business justification' principle?

A.
Producing separate business cases for each customer and supplier involved in the project
A.
Producing separate business cases for each customer and supplier involved in the project
Answers
B.
Defining the products that the project must produce in order to control change effectively
B.
Defining the products that the project must produce in order to control change effectively
Answers
C.
Establishing limits of authority on the project based on defined tolerances
C.
Establishing limits of authority on the project based on defined tolerances
Answers
D.
Adapting PRINCEZ to the scale of investment and the delivery approach
D.
Adapting PRINCEZ to the scale of investment and the delivery approach
Answers
Suggested answer: D

Explanation:

Achieving the principle of 'ensuring continued business justification' involves confirming that the project remains desirable, viable, and achievable throughout its lifecycle. Adapting PRINCE2 to the project's scale of investment and the chosen delivery approach helps maintain its alignment with business justification, ensuring that the project's scale, complexity, importance, capability, and risk are proportionate to the project's objectives and environment.

Reference: PRINCE2 7 Foundation handbook and documents on the principles of PRINCE2.

What is a purpose of the 'organizing practice?

A.
To define who is responsible for which project activities
A.
To define who is responsible for which project activities
Answers
B.
To compare the team's actual achievements against the team plan
B.
To compare the team's actual achievements against the team plan
Answers
C.
Ta understand what the users require of the project
C.
Ta understand what the users require of the project
Answers
D.
To assess modifications raised by team members
D.
To assess modifications raised by team members
Answers
Suggested answer: A

Explanation:

The purpose of the 'Organizing' practice within PRINCE2 is to establish and define the project management team structure and responsibilities. This includes specifying roles and responsibilities for managing, delivering, and overseeing the project effectively. The organization theme supports project success by ensuring clear definition and communication of who is responsible for various project activities.

Reference: PRINCE2 7 Foundation guide and official PRINCE2 documentation on organizing practices.

In which step of the risk management' technique should the organization's environment be considered?

A.
Identity
A.
Identity
Answers
B.
Assess
B.
Assess
Answers
C.
Plan
C.
Plan
Answers
D.
Implement
D.
Implement
Answers
Suggested answer: A

Explanation:

In the 'risk management' technique within PRINCE2, considering the organization's environment is essential during the 'Identify' step. This phase involves understanding the context in which the project operates, including external and internal factors that could affect the project. This context is crucial for identifying potential risks that could impact the project's objectives.

Reference: PRINCE2 7 Foundation resources on risk management technique.

Total 463 questions