Which should be funded from a change budget?

The Starting up a Project process
The Starting up a Project process
A fallback plan
A fallback plan
An agreed change to the scope of a project
An agreed change to the scope of a project
A change to a plan, within allocated tolerances, due to poor estimating
A change to a plan, within allocated tolerances, due to poor estimating
Comment (0)
Suggested answer: C
Explanation:

Similar to the answer to question 11, the change budget is specifically allocated for changes that are agreed upon that modify the scope of the project. This ensures that any scope modifications are funded without compromising the existing budget for planned deliverables.

Reference: PRINCE2 Foundation official study guide and online resources.