PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 43
List of questions
Question 421
According to the 'manage by exception' principle, which statement about tolerances is CORRECT?
Question 422
What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?
Question 423
Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?
Question 424
Which role is responsible for focusing on the safety and well-being of the project team?
Question 425
When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?
Question 426
Which should provide guidance on how and when prototyping is to be used?
Question 427
Which describes user's quality expectations?
Question 428
According to the 'exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
Question 429
Identify the missing word(s) in the following sentence:
[ ? ] dependency is one between two products of a project, over which the project team has control.
Question 430
Which action should the project manager take when reviewing progress to assess the 'health' of a stage?
Question