PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 43
List of questions
Related questions
According to the 'manage by exception' principle, which statement about tolerances is CORRECT?
What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?
Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?
Which role is responsible for focusing on the safety and well-being of the project team?
When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?
Which should provide guidance on how and when prototyping is to be used?
Which describes user's quality expectations?
According to the 'exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?
Identify the missing word(s) in the following sentence:
[ ? ] dependency is one between two products of a project, over which the project team has control.
Which action should the project manager take when reviewing progress to assess the 'health' of a stage?
Question