ExamGecko
Home Home / PRINCE2 / PRINCE2-7-Foundation

PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 8

Question list
Search
Search

Which is a purpose of the Initiating a Project process?

A.
Decide if it is worthwhile to initiate a project
A.
Decide if it is worthwhile to initiate a project
Answers
B.
Decide on the project approach
B.
Decide on the project approach
Answers
C.
Establish solid foundations for a project
C.
Establish solid foundations for a project
Answers
D.
Identify the number of Work Packages required
D.
Identify the number of Work Packages required
Answers
Suggested answer: C

Explanation:

The purpose of the Initiating a Project process is to establish solid foundations for the project, ensuring that there is a clear understanding of the reasons for the project, the benefits expected, and how the delivery will be managed. This foundation is crucial for the successful management and delivery of the project.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which is a purpose of the Managing Product Delivery process?

A.
Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
A.
Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
Answers
B.
Provide a controlled link between the Project Manager and the Team Manager(s)
B.
Provide a controlled link between the Project Manager and the Team Manager(s)
Answers
C.
Enable the Project Board to request updates to the current Team Plan
C.
Enable the Project Board to request updates to the current Team Plan
Answers
D.
Establish solid foundations for the project
D.
Establish solid foundations for the project
Answers
Suggested answer: B

Explanation:

The purpose of the Managing Product Delivery process is to ensure that there is a controlled link between the Project Manager and the Team Managers. This link facilitates the proper execution and delivery of Work Packages, ensuring that work is carried out effectively, monitored, and controlled.

Reference: PRINCE2 Foundation official documentation and study materials.

From whom does a Team Manager obtain approval for a completed product?

A.
Project Manager
A.
Project Manager
Answers
B.
Project Support
B.
Project Support
Answers
C.
The authority defined in the Product Description
C.
The authority defined in the Product Description
Answers
D.
Senior Supplier
D.
Senior Supplier
Answers
Suggested answer: A

Explanation:

In the PRINCE2 methodology, the Team Manager obtains approval for a completed product from the Project Manager. The Project Manager is responsible for ensuring that the products delivered by the Team Managers meet the project's standards and requirements before accepting them.

Reference: PRINCE2 Foundation official documentation and study materials.

Which is an objective of the Managing Product Delivery process?

A.
Sign-off completed Work Packages
A.
Sign-off completed Work Packages
Answers
B.
Ensure the Business Case is kept under review
B.
Ensure the Business Case is kept under review
Answers
C.
Report progress to the Project Board
C.
Report progress to the Project Board
Answers
D.
Ensure that work on products is authorized and agreed with the team
D.
Ensure that work on products is authorized and agreed with the team
Answers
Suggested answer: D

Explanation:

An objective of the Managing Product Delivery process is to ensure that work on products is authorized and agreed with the team. This process involves the Project Manager providing Work Packages to the Team Managers, who then complete the work agreed upon within the defined tolerances.

Reference: PRINCE2 Foundation official documentation and study materials.

What process aims to ensure accurate progress information is provided to the Project Manager?

A.
Starting up a Project
A.
Starting up a Project
Answers
B.
Managing a Stage Boundary
B.
Managing a Stage Boundary
Answers
C.
Managing Product Delivery
C.
Managing Product Delivery
Answers
D.
Directing a Project
D.
Directing a Project
Answers
Suggested answer: C

Explanation:

The process that aims to ensure accurate progress information is provided to the Project Manager is Managing Product Delivery. This process is essential for maintaining accurate communication about the status of the work being done, enabling the Project Manager to effectively monitor and control project progress.

Reference: PRINCE2 Foundation official documentation and study materials.

These responses are crafted based on the latest PRINCE2 Foundation guidelines and documentation, ensuring accuracy and compliance with the standards set by the PRINCE2 methodology.

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

A.
Closing a Project
A.
Closing a Project
Answers
B.
Managing a Stage Boundary
B.
Managing a Stage Boundary
Answers
C.
Managing Product Delivery
C.
Managing Product Delivery
Answers
D.
Directing a Project
D.
Directing a Project
Answers
Suggested answer: C

Explanation:

The Managing Product Delivery process in PRINCE2 covers the work done by external suppliers, even if they are not using PRINCE2. This process ensures that the work assigned to external suppliers is managed effectively, focusing on the acceptance, execution, and delivery of project products according to the agreed requirements.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which two roles are linked by the Managing Product Delivery process?

A.
Corporate or programme management and Project Board
A.
Corporate or programme management and Project Board
Answers
B.
Project Board and Project Manager
B.
Project Board and Project Manager
Answers
C.
Project Manager and Team Manager
C.
Project Manager and Team Manager
Answers
D.
Team Manager and external supplier
D.
Team Manager and external supplier
Answers
Suggested answer: C

Explanation:

The Managing Product Delivery process in PRINCE2 links the Project Manager and Team Manager roles. This connection is crucial as the Project Manager assigns work to the Team Manager, who is responsible for the production of the project's products, ensuring that the work is done to the right quality, at the right time, and within cost constraints.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

=========================

What is the collective name for individuals or groups who may be affected by a project?

A.
Customers
A.
Customers
Answers
B.
Project Support
B.
Project Support
Answers
C.
Stakeholders
C.
Stakeholders
Answers
D.
Team members
D.
Team members
Answers
Suggested answer: C

Explanation:

In PRINCE2, the collective name for individuals or groups who may be affected by or can influence a project is 'Stakeholders.' This includes a wide range of people such as customers, users, team members, and suppliers, each of whom has an interest in the project's successful execution and outcomes.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

A.
Create a separate Project Board to manage the supplier elements of the project
A.
Create a separate Project Board to manage the supplier elements of the project
Answers
B.
Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
B.
Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
Answers
C.
Create user and supplier groups
C.
Create user and supplier groups
Answers
D.
Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
D.
Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
Answers
Suggested answer: C

Explanation:

To control the size of the Project Board on a project that involves multiple users and suppliers, creating user and supplier groups is an effective strategy. These groups can represent broader interests and provide input to the Project Board, helping to streamline decision-making processes without overloading the board with members.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

When should the Project Board refer to corporate or programme management for a decision?

A.
The stage requires resources
A.
The stage requires resources
Answers
B.
It is forecast that project level tolerance will be exceeded
B.
It is forecast that project level tolerance will be exceeded
Answers
C.
The Senior Supplier or Senior User needs to be changed
C.
The Senior Supplier or Senior User needs to be changed
Answers
D.
Any request for change needs to be approved
D.
Any request for change needs to be approved
Answers
Suggested answer: B

Explanation:

The Project Board should refer to corporate or programme management for decisions when it is forecast that the project level tolerance will be exceeded. This scenario typically triggers an exception process as the predefined tolerances are fundamental limits within which the Project Board allows the Project Manager to manage the project.

Reference: PRINCE2 Foundation official study guide and materials.

Total 463 questions
Go to page: of 47