Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

A.
Benefits
A.
Benefits
Answers
B.
Quality
B.
Quality
Answers
C.
Risk
C.
Risk
Answers
D.
Scope
D.
Scope
Answers
Suggested answer: B

Explanation:

Quality is the aspect of project performance that must be managed to ensure the project's products are fit for purpose. PRINCE2 emphasizes that quality management is essential to ensure that the project outputs meet the necessary requirements and standards to achieve the desired outcomes.

Reference: PRINCE2 Foundation official documentation and study materials.

These responses are based on the latest materials and guidelines from the PRINCE2 Foundation, ensuring accurate and up-to-date answers as per your request.

Which is NOT included in the PRINCE2 definition of a project?

A.
A project is a temporary organization
A.
A project is a temporary organization
Answers
B.
A project's purpose is to deliver one or more business products
B.
A project's purpose is to deliver one or more business products
Answers
C.
A project is part of 'business as usual'
C.
A project is part of 'business as usual'
Answers
D.
A project is based on an agreed Business Case
D.
A project is based on an agreed Business Case
Answers
Suggested answer: C

Explanation:

According to PRINCE2, a project is not considered part of 'business as usual'. The defining attributes of a project include it being a temporary organization that is created for a specific purpose, which contrasts with 'business as usual' that involves ongoing, routine activities within an organization.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

A.
a corporate
A.
a corporate
Answers
B.
a temporary
B.
a temporary
Answers
C.
an external
C.
an external
Answers
D.
a technical
D.
a technical
Answers
Suggested answer: B

Explanation:

In PRINCE2, a project is defined as a temporary organization that is set up to deliver one or more business products according to an agreed Business Case. The temporary nature of projects highlights their finite and unique aspects, distinguishing them from regular, ongoing operations.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

A.
Principles
A.
Principles
Answers
B.
Themes
B.
Themes
Answers
C.
Processes
C.
Processes
Answers
D.
Techniques
D.
Techniques
Answers
Suggested answer: A

Explanation:

The guiding obligations and good practices which determine whether a project is genuinely being managed using PRINCE2 form the 'Principles' of the method. PRINCE2 is founded on seven principles that must be present in the project management approach to consider the project being managed using PRINCE2.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which is NOT one of the PRINCE2 integrated elements?

A.
Tailoring PRINCE2 to the project environment
A.
Tailoring PRINCE2 to the project environment
Answers
B.
The processes
B.
The processes
Answers
C.
The products
C.
The products
Answers
D.
The themes
D.
The themes
Answers
Suggested answer: C

Explanation:

In the context of PRINCE2, the integrated elements include the principles, themes, processes, and tailoring PRINCE2 to the project environment. 'The products' are not listed as one of these integrated elements. Instead, they are outputs or deliverables that result from applying the PRINCE2 methodology to project management.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

A.
Team Plan
A.
Team Plan
Answers
B.
Stage Plan
B.
Stage Plan
Answers
C.
Benefits Review Plan
C.
Benefits Review Plan
Answers
D.
Project Plan
D.
Project Plan
Answers
Suggested answer: B

Explanation:

During the Managing a Stage Boundary process, the Stage Plan for the next stage is created and submitted for approval. This plan outlines the work to be done in the upcoming stage and is a critical element for Project Board review before the next stage can commence.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which of the following is the Business Case used for during the Managing a Stage Boundary process?

A.
Enable the Project Board to decide whether or not to authorize the project
A.
Enable the Project Board to decide whether or not to authorize the project
Answers
B.
Justify the continuing viability of the project
B.
Justify the continuing viability of the project
Answers
C.
Enable the Project Board to decide whether or not to authorize project closure
C.
Enable the Project Board to decide whether or not to authorize project closure
Answers
D.
Justify the initiation of a project
D.
Justify the initiation of a project
Answers
Suggested answer: B

Explanation:

During the Managing a Stage Boundary process, the Business Case is used to justify the continuing viability of the project. This involves reviewing and, if necessary, updating the Business Case to reflect any changes or new insights that might impact the project's justification. This helps the Project Board make informed decisions about the future progression of the project.

Reference: PRINCE2 7 Foundation handbook and official documents.

Which activity takes place within the Managing a Stage Boundary process?

A.
Produce Highlight Reports
A.
Produce Highlight Reports
Answers
B.
Take corrective action within the limits of a stage's tolerance
B.
Take corrective action within the limits of a stage's tolerance
Answers
C.
Produce an Exception Plan
C.
Produce an Exception Plan
Answers
D.
Authorize a Stage Plan for the next stage
D.
Authorize a Stage Plan for the next stage
Answers
Suggested answer: C

Explanation:

Within the Managing a Stage Boundary process, one of the key activities is to produce an Exception Plan. This occurs when the current stage plan cannot be completed within the agreed tolerances. An Exception Plan is needed to replace the Stage Plan for the current stage and requires approval from the Project Board before it can be executed.

Reference: PRINCE2 7 Foundation resources and study materials.

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

A.
Managing Product Delivery
A.
Managing Product Delivery
Answers
B.
Initiating a Project
B.
Initiating a Project
Answers
C.
Managing a Stage Boundary
C.
Managing a Stage Boundary
Answers
D.
Starting up a Project
D.
Starting up a Project
Answers
Suggested answer: D

Explanation:

The process that ensures key roles and responsibilities are allocated before a decision is made to initiate a project is 'Starting up a Project'. This process is crucial as it involves the appointment of the project management team and ensures that there is a clear understanding of the project's initial structure and approach before formally initiating the project.

Reference: PRINCE2 7 Foundation handbook and documents.

Which is a purpose of a Project Brief?

A.
Enable the assembly of the project mandate
A.
Enable the assembly of the project mandate
Answers
B.
Describe the reporting requirements of the various layers of management involved with the project
B.
Describe the reporting requirements of the various layers of management involved with the project
Answers
C.
Describe how changes to products will be controlled
C.
Describe how changes to products will be controlled
Answers
D.
Provide a solid basis for the initiation of the project
D.
Provide a solid basis for the initiation of the project
Answers
Suggested answer: D

Explanation:

The purpose of a Project Brief in PRINCE2 is to provide a solid basis for the initiation of the project. The Project Brief includes the outline of the project's objectives, scope, constraints, and assumptions. It is developed during the 'Starting up a Project' process and is used to ensure that a clear, concise, and feasible plan is proposed before the project is formally initiated.

Reference: PRINCE2 7 Foundation resources and materials.