Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

A.
Specify the desired result
A.
Specify the desired result
Answers
B.
Provide the resources and skills to deliver the desired result
B.
Provide the resources and skills to deliver the desired result
Answers
C.
Ensure the technical integrity of a project
C.
Ensure the technical integrity of a project
Answers
D.
Develop a project's products
D.
Develop a project's products
Answers
Suggested answer: A

Explanation:

In the PRINCE2 customer/supplier environment, it is typically the customer's responsibility to specify the desired result of the project. This responsibility involves defining what the project should achieve in terms of outcomes and benefits, aligning with the customer's business objectives.

Reference: PRINCE2 Foundation official study materials.

Which is a benefit of using PRINCE2?

A.
Enables the management of projects as well as of 'business as usual' activities
A.
Enables the management of projects as well as of 'business as usual' activities
Answers
B.
Can be tailored by leaving out elements of the method for some projects
B.
Can be tailored by leaving out elements of the method for some projects
Answers
C.
Can be applied to any type of project
C.
Can be applied to any type of project
Answers
D.
Avoids the need to involve corporate or programme management
D.
Avoids the need to involve corporate or programme management
Answers
Suggested answer: C

Explanation:

One of the key benefits of using PRINCE2 is its versatility and adaptability, meaning it can be applied to any type of project across various industries. This flexibility is one of the reasons PRINCE2 is widely adopted globally.

Reference: PRINCE2 Foundation official study materials.

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

A.
Manage by stages
A.
Manage by stages
Answers
B.
Manage by exception
B.
Manage by exception
Answers
C.
Continued business justification
C.
Continued business justification
Answers
D.
Learn from experience
D.
Learn from experience
Answers
Suggested answer: B

Explanation:

The PRINCE2 principle supported by the setting of tolerances for the three levels of plan (Project, Stage, and Team Plans) is 'Manage by exception.' This principle allows management to set predefined tolerances for project objectives, and only escalate issues to higher management if these tolerances are exceeded, thereby facilitating efficient use of management time and focus.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Which role is responsible for creating Checkpoint Reports?

A.
Senior Supplier
A.
Senior Supplier
Answers
B.
Team Manager
B.
Team Manager
Answers
C.
Change Authority
C.
Change Authority
Answers
D.
Project Support
D.
Project Support
Answers
Suggested answer: B

Explanation:

In PRINCE2, the Team Manager is responsible for creating Checkpoint Reports. These reports provide the Project Manager with a summary of the progress within a Work Package, detailing performance against plan, and highlighting any issues that might affect the work.

Reference: PRINCE2 Foundation official study materials.

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

A.
project cost tolerance
A.
project cost tolerance
Answers
B.
stage cost tolerance
B.
stage cost tolerance
Answers
C.
Work Package cost tolerance
C.
Work Package cost tolerance
Answers
D.
product cost tolerance
D.
product cost tolerance
Answers
Suggested answer: C

Explanation:

A Project Manager agrees on the Work Package cost tolerances with a Team Manager. This agreement defines the acceptable cost variance within which the Team Manager can operate without needing further approval.

Reference: PRINCE2 Foundation official study materials.

Which statement about stages is true?

A.
Management stages should be of the same duration
A.
Management stages should be of the same duration
Answers
B.
The use of technical stages is mandatory
B.
The use of technical stages is mandatory
Answers
C.
The use of management stages is mandatory
C.
The use of management stages is mandatory
Answers
D.
Management stages are driven by specialist teams
D.
Management stages are driven by specialist teams
Answers
Suggested answer: C

Explanation:

PRINCE2 mandates the use of management stages in project management. These stages are critical control points used by the Project Board to review progress, assess risks, and make decisions about the project's future. This structure allows for regular monitoring and controlling of the project by breaking it down into manageable sections.

Reference: PRINCE2 Foundation official documentation and study materials.

What product defines the reporting requirements between the Project Manager and Team Manager?

A.
Project Brief
A.
Project Brief
Answers
B.
Product Description
B.
Product Description
Answers
C.
Team Plan
C.
Team Plan
Answers
D.
Work Package
D.
Work Package
Answers
Suggested answer: D

Explanation:

The Work Package is the product that defines the reporting requirements between the Project Manager and the Team Manager. It describes the work, specifies the product's description, and sets out the reporting requirements among other information, ensuring that both managers have clear guidelines on communications regarding the package's delivery.

Reference: PRINCE2 Foundation official documentation and study materials.

Whose approval is needed to replace a Stage Plan with an Exception Plan?

A.
Corporate or programme management
A.
Corporate or programme management
Answers
B.
Project Board
B.
Project Board
Answers
C.
Project Manager
C.
Project Manager
Answers
D.
Team Manager
D.
Team Manager
Answers
Suggested answer: B

Explanation:

The approval needed to replace a Stage Plan with an Exception Plan must come from the Project Board. This is because the Exception Plan is created when a Stage Plan is forecast to exceed its tolerance levels, and the Project Board is responsible for approving such significant changes in the project's direction or management.

Reference: PRINCE2 Foundation official documentation and study materials.

Which is a difference between management and technical stages?

A.
Management stages require planning and technical stages do not
A.
Management stages require planning and technical stages do not
Answers
B.
Technical stages can overlap and management stages cannot
B.
Technical stages can overlap and management stages cannot
Answers
C.
Management stages deliver products and technical stages do not
C.
Management stages deliver products and technical stages do not
Answers
D.
Technical stages require resources and management stages do not
D.
Technical stages require resources and management stages do not
Answers
Suggested answer: B

Explanation:

A key difference between management and technical stages in PRINCE2 is that technical stages can overlap whereas management stages cannot. Technical stages refer to the actual work being done, which can sometimes proceed in parallel, while management stages are concerned with the control and decision points that must be sequential to ensure proper governance.

Reference: PRINCE2 Foundation official documentation and study materials.

Which product identifies the management stages and timescales of a project?

A.
Project Brief
A.
Project Brief
Answers
B.
Project Product Description
B.
Project Product Description
Answers
C.
Project Plan
C.
Project Plan
Answers
D.
Initiation Stage Plan
D.
Initiation Stage Plan
Answers
Suggested answer: C

Explanation:

The Project Plan in PRINCE2 identifies the management stages and timescales of a project. This plan provides an overview of how and when the project's objectives are to be achieved, by showing the major products, activities and resources required for the project, and structuring them within a timescale.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources