Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

Stage Plan
Stage Plan
Communication Management Strategy
Communication Management Strategy
Follow-on action recommendations
Follow-on action recommendations
Quality Management Strategy
Quality Management Strategy
Suggested answer: B
Explanation:

The Communication Management Strategy should be referred to at the end of a stage to check whether there is a requirement to send copies of the End Stage Report to external interested parties. This document outlines how, when, and by whom information will be disseminated throughout the project, including communication with external stakeholders.

Reference: PRINCE2 Foundation official study guide and materials.

asked 23/09/2024
Ahti Paju
37 questions

Question 82

Report Export Collapse

Which is NOT a purpose of the Organization theme?

Define a project management team structure
Define a project management team structure
Define the level of tolerance for each level of the project management team
Define the level of tolerance for each level of the project management team
Define the Project Board's responsibility for directing the project
Define the Project Board's responsibility for directing the project
Define which role is accountable for the project's success
Define which role is accountable for the project's success
Suggested answer: B
Explanation:

The Organization theme does not include defining the level of tolerance for each level of the project management team. Tolerance levels are typically set within the Plans theme, which deals with how the project is structured in terms of stages and the delegation of authority within those tolerances. The Organization theme primarily focuses on defining roles and responsibilities.

Reference: PRINCE2 Foundation official study guide and materials.

asked 23/09/2024
Monique Canham
42 questions

Question 83

Report Export Collapse

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

Those with a financial interest in the project
Those with a financial interest in the project
Those who will manage the project on a day-to-day basis
Those who will manage the project on a day-to-day basis
Those who will specify the desired outputs of the project
Those who will specify the desired outputs of the project
Those who will create the project's outputs
Those who will create the project's outputs
Suggested answer: A
Explanation:

PRINCE2 identifies three primary categories of stakeholders: 1) those who will specify the desired outputs (customers/users), 2) those who will manage the project on a day-to-day basis (suppliers), and 3) those who use the project's outputs. Those with a financial interest in the project are not explicitly categorized as one of the primary stakeholder types in PRINCE2.

Reference: PRINCE2 Foundation official study guide and materials.

asked 23/09/2024
Jaap van Veldhuizen
51 questions

Question 84

Report Export Collapse

Which does the Executive need to ensure is in place before the project is initiated?

All Work Packages are authorized
All Work Packages are authorized
An understanding of how the project will contribute to corporate objectives
An understanding of how the project will contribute to corporate objectives
The Project Plan has been approved
The Project Plan has been approved
The Project Initiation Documentation is complete
The Project Initiation Documentation is complete
Suggested answer: B
Explanation:

Before initiating a project, the Executive in PRINCE2 needs to ensure there is a clear understanding of how the project will contribute to the corporate objectives. This alignment is crucial for justifying the project's existence and ensuring it has a clear business purpose and expected benefits that support the organization's strategic goals.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Jose Leston
47 questions

Question 85

Report Export Collapse

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

Executive
Executive
Senior User
Senior User
Senior Supplier
Senior Supplier
Project Manager
Project Manager
Suggested answer: B
Explanation:

The Senior User within the PRINCE2 project management team represents the interests of those who will use the project's products and benefit from their operation after the project is complete. This role is responsible for specifying the needs of users, ensuring the solution meets these needs, and is capable of delivering the anticipated benefits.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Mohamed Khazem
27 questions

Question 86

Report Export Collapse

What product is used to maintain a record of those who have an interest in the project and their information requirements?

Project Plan
Project Plan
Communication Management Strategy
Communication Management Strategy
Project Brief
Project Brief
Project Product Description
Project Product Description
Suggested answer: B
Explanation:

The Communication Management Strategy is used in PRINCE2 to maintain a record of stakeholders who have an interest in the project and their information requirements. This document outlines how and when stakeholders will be kept informed about the project's progress and any issues that may arise.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
martin lopez
29 questions

Question 87

Report Export Collapse

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

quality
quality
supplier
supplier
risk
risk
product
product
Suggested answer: A
Explanation:

A member of the Project Board is responsible for quality assurance in PRINCE2. Quality assurance is concerned with ensuring that the project's products meet the quality requirements set out in the project and that the project adheres to the appropriate corporate, programme management, or customer quality standards.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

asked 23/09/2024
Mark Oh
38 questions

Question 88

Report Export Collapse

How many roles make up the Project Board?

One
One
Two
Two
Three
Three
Four
Four
Suggested answer: C
Explanation:

The Project Board within the PRINCE2 framework is made up of three key roles: the Executive, the Senior User, and the Senior Supplier. These roles represent the business, user, and supplier interests respectively, ensuring that the project's decision-making is balanced across these three perspectives.

Reference: PRINCE2 Foundation official documentation and study materials.

asked 23/09/2024
Diogo Vitor
42 questions

Question 89

Report Export Collapse

Which of the following statements about stakeholders are true?

1. Someone who thinks they will be affected by a project is a stakeholder on that project.

2. Stakeholders may be internal or external to the corporate organization.

Only 1 is true
Only 1 is true
Only 2 is true
Only 2 is true
Both 1 and 2 are true
Both 1 and 2 are true
Neither 1 or 2 are true
Neither 1 or 2 are true
Suggested answer: C
Explanation:

Both statements about stakeholders are true in the context of PRINCE2. A stakeholder in a project includes anyone who thinks they will be affected by the project, which can include both supporters and those who may oppose the project. Additionally, stakeholders can be both internal and external to the organization that is undertaking the project.

Reference: PRINCE2 Foundation official documentation and study materials.

asked 23/09/2024
Bill May
50 questions

Question 90

Report Export Collapse

Which is one of the six aspects of project performance that needs to be managed?

Progress
Progress
Change
Change
Risk
Risk
Security
Security
Suggested answer: A
Explanation:

Among the six aspects of project performance that need to be managed according to PRINCE2, 'Progress' is a key component. The other aspects include costs, timescales, quality, scope, risk, and benefits. Managing progress involves monitoring and controlling how far along the project is in achieving its objectives and delivering its products.

Reference: PRINCE2 Foundation official documentation and study materials.

asked 23/09/2024
ABDUL AZEEZ
37 questions
Total 463 questions
Go to page: of 47