Identify the missing word in the following sentence.

An (?) is the result of change, normally affecting real-world behavior and circumstances:

A.
outcome
A.
outcome
Answers
B.
exception
B.
exception
Answers
C.
output
C.
output
Answers
D.
off-specification
D.
off-specification
Answers
Suggested answer: A

Explanation:

In PRINCE2 terminology, an 'outcome' is defined as the result of change, generally manifested as benefits or alterations in real-world behavior and circumstances. Outcomes are distinct from outputs (specific deliverables or products of the project) as they reflect the longer-term impacts and changes brought about by utilizing those outputs.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Which TWO are objectives of the closing a project: process?

1. To ensure the benefit reviews enable the project benefits to the confirmed

2. To update the business case so that the project hoard can decide whether to continue with the project

3. To ensure that the project team deliver the products to quality expectations

4. To hand over any open threats to operations

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: D

Explanation:

The objectives of the 'Closing a Project' process in PRINCE2 include ensuring that provisions are made for ongoing benefit realization reviews (objective 1) and handing over any ongoing issues, including unresolved risks or threats, to operational maintenance or support teams (objective 4). This process is about wrapping up the project cleanly, ensuring that all project objectives related to closure are met, and preparing for the sustained realization of benefits post-project.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

A.
Quality register
A.
Quality register
Answers
B.
Project plan
B.
Project plan
Answers
C.
Project product description
C.
Project product description
Answers
D.
Quality management approach
D.
Quality management approach
Answers
Suggested answer: C

Explanation:

The Project Product Description in PRINCE2 is a document where the project manager records specific requirements that must be met for the user to accept the final product, including criteria for user satisfaction. This document provides a detailed description of the purpose, composition, derivation, and quality criteria of the project's main deliverable or product.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Which details the identified threats and Opportunities related in the project?

A.
Risk management approach
A.
Risk management approach
Answers
B.
Project plan
B.
Project plan
Answers
C.
Risk register
C.
Risk register
Answers
D.
Business case
D.
Business case
Answers
Suggested answer: C

Explanation:

The Risk Register in PRINCE2 is a document used to detail all identified risks associated with the project, including both threats and opportunities. This register includes descriptions of each risk, their status, and the responses planned or taken to manage these risks, serving as a key tool for risk management throughout the project lifecycle.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Which member of the project management team should secure funding for the project before the project stars?

A.
Project executive
A.
Project executive
Answers
B.
Project manager
B.
Project manager
Answers
C.
Senior user
C.
Senior user
Answers
D.
senior supplier
D.
senior supplier
Answers
Suggested answer: A

Explanation:

In PRINCE2, the Project Executive is responsible for the overall success of the project, which includes securing the necessary funding before the project begins. This role is part of the project board and has the authority to commit organizational resources and funds, ensuring that the project is financially viable from start to finish.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Which should define how tools will be used to support the information needs of the project team?

A.
Digital and data management approach
A.
Digital and data management approach
Answers
B.
Quality management approach
B.
Quality management approach
Answers
C.
Issue management approach
C.
Issue management approach
Answers
D.
Commercial management approach
D.
Commercial management approach
Answers
Suggested answer: A

Explanation:

The 'Digital and Data Management Approach' in PRINCE2 should define how tools and technologies will be utilized to support the information needs of the project team. This approach outlines how digital resources, data handling, and communication tools are to be deployed to enhance the effectiveness of information sharing and project management practices.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Identify the missing ward in the following sentence.

PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.

A.
project team
A.
project team
Answers
B.
project management team structure
B.
project management team structure
Answers
C.
project bard
C.
project bard
Answers
D.
project assurance
D.
project assurance
Answers
Suggested answer: A

Explanation:

In PRINCE2, the term 'project team' encompasses all individuals who are allocated time and responsibilities on the project, covering both the project management team and the wider team members who work on the project's tasks. This terminology includes everyone contributing to the project's delivery.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

The project management team heeds t document quality antral events, such as testing

According to the guidance for effective quality management, haw should the events be documented?

A.
In stage of team plans to allow mare accurate scheduling
A.
In stage of team plans to allow mare accurate scheduling
Answers
B.
As quality tolerances in product descriptions
B.
As quality tolerances in product descriptions
Answers
C.
As acceptance criteria in the project product description
C.
As acceptance criteria in the project product description
Answers
D.
In the quality management approach to plan the testing
D.
In the quality management approach to plan the testing
Answers
Suggested answer: D

Explanation:

Quality control events, such as testing, should be documented in the 'Quality Management Approach' according to PRINCE2 guidelines. This document outlines how quality will be managed throughout the project, detailing specific methods and events, including schedules for quality assurance activities and testing, to ensure that products meet their defined quality criteria.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

In which process should the specified quality methods he used to/prove that a product meets its quality criteria?

A.
Managing product delivery
A.
Managing product delivery
Answers
B.
controlling a stage
B.
controlling a stage
Answers
C.
Managing a stage boundary
C.
Managing a stage boundary
Answers
D.
closing a project
D.
closing a project
Answers
Suggested answer: A

Explanation:

The 'Managing Product Delivery' process in PRINCE2 is where the specified quality methods are applied to ensure that a product meets its quality criteria. This process focuses on the acceptance, execution, and delivery of the project's products, ensuring that they are produced to the defined quality standards as part of the overall project delivery.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Which statement describes a purpose of the 'starting up a project' process?

A.
To appoint people ta the major rales in the project management team
A.
To appoint people ta the major rales in the project management team
Answers
B.
Ta agree how a team manager will report progress
B.
Ta agree how a team manager will report progress
Answers
C.
To provide Information so that the business can understand the cost of delivering the project
C.
To provide Information so that the business can understand the cost of delivering the project
Answers
D.
To provide management control Listen the project manager and the team managers
D.
To provide management control Listen the project manager and the team managers
Answers
Suggested answer: A

Explanation:

The purpose of the 'Starting up a Project' process is primarily to appoint people to the major roles within the project management team. This process ensures that the right people are in place with clear responsibilities before the project kicks off, facilitating effective planning and execution from the outset.

Reference: PRINCE2 7 Foundation manual and the 'Starting up a Project' process documentation.

Total 463 questions