Whitt is 3 purpose of the initiating a project' process?

A.
To prepare the contract for the project to enable the project board to commit to delivery
A.
To prepare the contract for the project to enable the project board to commit to delivery
Answers
B.
To provide the project board with Just Enough Information to decide whether to approve the Initiation stage
B.
To provide the project board with Just Enough Information to decide whether to approve the Initiation stage
Answers
C.
To provide the opportunity for the senior user in confirm that they find the project product acceptable
C.
To provide the opportunity for the senior user in confirm that they find the project product acceptable
Answers
D.
To enable the project board to empower the project manager to work within delegated authority limits
D.
To enable the project board to empower the project manager to work within delegated authority limits
Answers
Suggested answer: B

Explanation:

The purpose of the 'Initiating a Project' process is to provide the Project Board with just enough information to decide whether to approve the initiation stage. This process involves the development of a more detailed Business Case and Project Plan, which are crucial for the Project Board to assess the project's viability and decide on its initiation confidently.

Reference: PRINCE2 official guide and syllabus.

According to the 'exception management' technique, when should the team manager raise an issue?

A.
When the team manager predicts that a product will cause a stage to exceed its time tolerance
A.
When the team manager predicts that a product will cause a stage to exceed its time tolerance
Answers
B.
When the team manager identifies that a product is going to be delivered late
B.
When the team manager identifies that a product is going to be delivered late
Answers
C.
when the team manager predicts that a product will cause a work package to exceed its time tolerance
C.
when the team manager predicts that a product will cause a work package to exceed its time tolerance
Answers
D.
when the team manager identifies that the work package has already exceeded its time tolerance
D.
when the team manager identifies that the work package has already exceeded its time tolerance
Answers
Suggested answer: C

Explanation:

According to the 'exception management' technique, the team manager should raise an issue when they predict that a product will cause a work package to exceed its time tolerance. This proactive approach allows for timely decision-making and corrective action by the Project Board, ensuring that project delivery is kept on track and within the agreed tolerances.

Reference: PRINCE2 methodology and exception management guidance.

Which TWO are objectives of the 'controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage's products meet-agreed quality expectations

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: D

Explanation:

The objectives of the 'Controlling a Stage' process in PRINCE2 include focusing on the completion of work within agreed tolerances and ensuring that all stage products meet the agreed quality expectations. These objectives are central to maintaining control over the stage and ensuring that the project delivers outputs that are fit for purpose.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

A.
Increase the frequency of checkpoint reports
A.
Increase the frequency of checkpoint reports
Answers
B.
Allow the team manager more flexibility to exceed cost tolerance
B.
Allow the team manager more flexibility to exceed cost tolerance
Answers
C.
Increase the frequency of event-driven controls
C.
Increase the frequency of event-driven controls
Answers
D.
Increase the frequency of escalations by the team manager
D.
Increase the frequency of escalations by the team manager
Answers
Suggested answer: A

Explanation:

When a team manager is inexperienced, increasing the frequency of checkpoint reports can provide the project manager with more frequent updates on progress and issues. This allows for quicker identification and resolution of problems, thus maintaining better control over the project's progress and supporting the team manager more effectively.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

How can the risk culture of 3n organization make decision-making less effective?

A.
By using statistical modelling be understand the Impact of risks and their likelihood
A.
By using statistical modelling be understand the Impact of risks and their likelihood
Answers
B.
By establishing a risk budget to make funding risk responses actions easier
B.
By establishing a risk budget to make funding risk responses actions easier
Answers
C.
By Individuals adopting an attitude that leads them to ignore threats to objectives
C.
By Individuals adopting an attitude that leads them to ignore threats to objectives
Answers
D.
By Involving stakeholders in assessing the likelihood and impact of each risk
D.
By Involving stakeholders in assessing the likelihood and impact of each risk
Answers
Suggested answer: C

Explanation:

The risk culture of an organization can make decision-making less effective when individuals adopt an attitude that leads them to ignore threats to objectives. This behavior results in underestimating or neglecting the potential impacts of risks, which can compromise the decision-making process and lead to less effective risk management and project outcomes.

Reference: PRINCE2 7 Foundation training materials and risk management guidelines.

A new team member has joined the project team and wants to understand who else is on the project team, and who they report to.

Which management product should the team member review?

A.
Project plan
A.
Project plan
Answers
B.
Project management team structure
B.
Project management team structure
Answers
C.
Role descriptions
C.
Role descriptions
Answers
D.
Project log
D.
Project log
Answers
Suggested answer: C

Explanation:

A new team member looking to understand the project team structure and reporting lines should review the 'Role Descriptions'. This management product provides detailed information about each role within the project, including responsibilities and reporting relationships, which helps new members understand their place within the team and to whom they report.

Reference: PRINCE2 Foundation official guide and project management templates.

Which term is defined-as the amount and type or risk that the business is willing to take in pursuit of is objectives?

A.
Risk appetite
A.
Risk appetite
Answers
B.
Opportunity
B.
Opportunity
Answers
C.
Risk tolerance
C.
Risk tolerance
Answers
D.
Risk cause
D.
Risk cause
Answers
Suggested answer: A

Explanation:

Risk appetite is defined as the amount and type of risk that an organization is willing to take in pursuit of its objectives. This concept helps organizations balance the potential benefits of risk-taking with their capability to manage the impact of unfavorable outcomes.

Reference: PRINCE2 training manual and risk management framework.

The project manager reviews whether there has been a Change in the way team members relate to each other.

Which principle is the project manager applying as part of the 'people' element?

A.
Manage by stages
A.
Manage by stages
Answers
B.
Focus on products
B.
Focus on products
Answers
C.
Tailor to suit the project context
C.
Tailor to suit the project context
Answers
D.
Learn from experience
D.
Learn from experience
Answers
Suggested answer: C

Explanation:

The principle that the project manager is applying by reviewing changes in team dynamics is 'Tailor to suit the project context'. This principle involves adapting the management of the project to the environment, including the team dynamics, to ensure that the project management approach is appropriate for the specific context and challenges of the project.

Reference: PRINCE2 7 Foundation handbook and principles section.

In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?

A.
Preparing estimates
A.
Preparing estimates
Answers
B.
Defining and analyzing the products
B.
Defining and analyzing the products
Answers
C.
Organizing work packages
C.
Organizing work packages
Answers
D.
Preparing a schedule
D.
Preparing a schedule
Answers
Suggested answer: A

Explanation:

In the 'planning' technique, a team manager should break down the cost of delivering a work package during the 'Preparing estimates' step. This involves estimating the resources and time required to deliver each component of the work package, which are critical for budgeting and resource allocation.

Reference: PRINCE2 Foundation course material on planning techniques and project management documentation.

Topic 4, Exam Pool D

Why is change management important in a project?

A.
It provides clarity on how the culture of an organization needs to adapt over time
A.
It provides clarity on how the culture of an organization needs to adapt over time
Answers
B.
It provides processes and management products to use when requesting a change
B.
It provides processes and management products to use when requesting a change
Answers
C.
It provides confidence that the project can meet is objectives and has continued business Justification
C.
It provides confidence that the project can meet is objectives and has continued business Justification
Answers
D.
It provides a controlled and bidirectional flow of information to key Influencers
D.
It provides a controlled and bidirectional flow of information to key Influencers
Answers
Suggested answer: B

Explanation:

Change management is important in a project because it provides structured processes and management products to manage and implement changes effectively. This ensures that all changes are assessed, approved, managed, and documented properly, helping the project adapt to changes while maintaining control and alignment with project objectives.

Reference: PRINCE2 Foundation official resources and training on change management.