PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 36
List of questions
Question 351
The project manager needs to document how risk management will be undertaken during the project.
In which step of the 'risk management' technique should the project manager document this?
Question 352
Which principle should ensure that a project remains aligned with the objectives of the investing organizations?
Question 353
Which statement BEST describes how approved plans enable control?
Question 354
The senior user needs to ensure that the outputs will be used effectively to achieve the autcomes and realize the benefits.
Which element of effective business case management is the senior user applying?
Question 355
Which process has the objective of confirming that acceptance criteria have been met?
Question 356
When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.
Question 357
Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:
Which role should be accountable for approving these proposals?
Question 358
What is a purpose of the communication management approach?
Question 359
The project board needs to confirm that there is enough information to initiate the project.
What should the project board review?
Question 360
Which term is defined as the means by which an organization transitions from its current state to the target state?
Question