Identify the missing words in the following sentence.

The 'starting up a project' process is triggered when a [ ? J is available.

A.
project business case
A.
project business case
Answers
B.
project mandate
B.
project mandate
Answers
C.
stage plan
C.
stage plan
Answers
D.
work package
D.
work package
Answers
Suggested answer: B

Explanation:

The 'Starting up a Project' process in PRINCE2 is typically triggered when a project mandate is available. The project mandate provides the basic information necessary to define whether there is sufficient justification to proceed with the project's setup.

Reference: PRINCE2 Foundation Manual

Which is an objective of the 'directing a project' process?

A.
To create the plan to deliver the project product
A.
To create the plan to deliver the project product
Answers
B.
To select and appoint the project manager
B.
To select and appoint the project manager
Answers
C.
To design the project management team roles
C.
To design the project management team roles
Answers
D.
To give authority to deliver the project product
D.
To give authority to deliver the project product
Answers
Suggested answer: D

Explanation:

An objective of the 'Directing a Project' process in PRINCE2 is to give authority to deliver the project product. This process is where the project board makes key decisions and exercises overall control while delegating day-to-day management of the project stages to the project manager.

Reference: PRINCE2 Foundation Manual

What is established during the 'initiating a project' process?

A.
The agreed protect acceptance criteria
A.
The agreed protect acceptance criteria
Answers
B.
The need for a configuration library
B.
The need for a configuration library
Answers
C.
A plan for the work or project initiation
C.
A plan for the work or project initiation
Answers
D.
An understanding of the project's funding
D.
An understanding of the project's funding
Answers
Suggested answer: C

Explanation:

During the 'Initiating a Project' process in PRINCE2, a detailed plan for the work needed for project initiation is established. This includes developing the various management strategies and the project initiation documentation (PID) that will guide the project's execution and control phases.

Reference: PRINCE2 Foundation Manual

Which is an objective of the 'controlling a stage' process?

A.
To review the business justification for the project
A.
To review the business justification for the project
Answers
B.
To replan the current stage when directed
B.
To replan the current stage when directed
Answers
C.
To develop products to defined quality criteria
C.
To develop products to defined quality criteria
Answers
D.
To produce a learn plan for the work package
D.
To produce a learn plan for the work package
Answers
Suggested answer: B

Explanation:

An objective of the 'Controlling a Stage' process in PRINCE2 is to replan the current stage when directed. This process handles day-to-day management of the project, and includes responding to issues that might impact the stage plan, requiring replanning to ensure project objectives can still be met.

Reference: PRINCE2 Foundation Manual

Which is a feature of PRINCE2?

A.
It is naturally right=sized to the scale of every project
A.
It is naturally right=sized to the scale of every project
Answers
B.
It promotes improving processes for every project
B.
It promotes improving processes for every project
Answers
C.
It replaces the need to apply specialist Industry-specific lifecycles
C.
It replaces the need to apply specialist Industry-specific lifecycles
Answers
D.
It focuses on completing the project on time as its main objective
D.
It focuses on completing the project on time as its main objective
Answers
Suggested answer: A

Explanation:

PRINCE2 is flexible and can be tailored to fit the size, complexity, importance, capability, and risk of the project. This adaptability is a key feature of PRINCE2, ensuring that the methodology can be scaled up or down to suit the specific demands of different projects.

Reference: PRINCE2 7 Foundation handbook and official documentation on PRINCE2 features.

In which step of the 'risk management technique should the organization's environment be considered?

A.
Identify
A.
Identify
Answers
B.
Assess
B.
Assess
Answers
C.
Plan
C.
Plan
Answers
D.
Implement
D.
Implement
Answers
Suggested answer: A

Explanation:

Similar to question 397, the correct answer for considering the organization's environment in the risk management technique is during the 'Identify' step. This initial phase of risk management involves recognizing and recording risks after considering various environmental factors that can influence the project.

Reference: PRINCE2 7 Foundation guide on risk management.

How does product-based planning help to determine the project approach?

A.
By Identifying the outputs that the project trust deliver
A.
By Identifying the outputs that the project trust deliver
Answers
B.
By planning in detail how to deliver the outputs over a more predictable time scale
B.
By planning in detail how to deliver the outputs over a more predictable time scale
Answers
C.
By managing constraints to the planned completion date for the project
C.
By managing constraints to the planned completion date for the project
Answers
D.
By dividing the delivery of the project's outputs into stages which do not overlap
D.
By dividing the delivery of the project's outputs into stages which do not overlap
Answers
Suggested answer: A

Explanation:

Product-based planning in PRINCE2 focuses on defining and understanding the project's outputs or products. This method helps in determining the project's approach by clarifying what products must be delivered, thus guiding the planning of activities and resources needed to create these products. It ensures that the project's structure and execution strategy are aligned with delivering tangible, well-defined outcomes.

Reference: PRINCE2 7 Foundation resources on product-based planning.

Which plan should only be produced if the project is large and complex enough?

A.
Project plan
A.
Project plan
Answers
B.
Stags plan
B.
Stags plan
Answers
C.
Team plan
C.
Team plan
Answers
D.
Exception plan
D.
Exception plan
Answers
Suggested answer: C

Explanation:

In PRINCE2, a Team Plan is a type of plan that might only be produced for very large or complex projects. It is typically more detailed and is specifically designed to manage a segment of the project within a certain team or group. This plan provides detailed guidance on the delivery of the products assigned to the team within the constraints set by the Stage Plan.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

How do issue management and change control relate to each other?

A.
Change control and Issue management are separate processes
A.
Change control and Issue management are separate processes
Answers
B.
Issue management is part of change control
B.
Issue management is part of change control
Answers
C.
change control is part of issue management
C.
change control is part of issue management
Answers
D.
issue management and change control are identical
D.
issue management and change control are identical
Answers
Suggested answer: B

Explanation:

In PRINCE2, issue management and change control are closely related, where issue management is considered a subset of change control. Change control is a broader process that encompasses all aspects of managing changes within the project, including issues that might impact the project's scope, timescales, costs, or quality. Issue management specifically deals with resolving issues that can affect the progress of the project.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)

The project manager has asked for a report to check whether there are any conflicts between the agreed state of the products and the actual products being worked on.

Which part of effective issue management is the project manager applying?

A.
Baselines
A.
Baselines
Answers
B.
Change budget
B.
Change budget
Answers
C.
Change control
C.
Change control
Answers
D.
Issue resolution
D.
Issue resolution
Answers
Suggested answer: A

Explanation:

In PRINCE2, baselines are used to establish a reference point for the agreed state of products, against which actual progress can be compared and managed. By requesting a report to check for conflicts between the agreed and actual states of products, the project manager is effectively applying the concept of baselines within issue management. This helps in identifying deviations from the agreed deliverables and initiating corrective actions to address these discrepancies.

Reference: (PRINCE2 7 Foundation Handbook, AXELOS)