ExamGecko
Home Home / PRINCE2 / PRINCE2-7-Foundation

PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 33

Question list
Search
Search

Which activity is part of the recommended risk management procedure?

A.
Allocating a budget to investigate issues
A.
Allocating a budget to investigate issues
Answers
B.
Reviewing risk management practices to ensure that they are performing effectively
B.
Reviewing risk management practices to ensure that they are performing effectively
Answers
C.
Sending information to stakeholders about risks to the projects
C.
Sending information to stakeholders about risks to the projects
Answers
D.
Resolving conflicts between the project and the programme board
D.
Resolving conflicts between the project and the programme board
Answers
Suggested answer: B

Explanation:

Part of the recommended risk management procedure in PRINCE2 includes regularly reviewing risk management practices to ensure they are effective. This activity involves evaluating the processes used for risk identification, assessment, and response to ensure that risks are being managed appropriately and that the procedures are fit for purpose.

Reference: PRINCE2 Foundation Manual

Which management product is used to record relationships between specialist products?

A.
Change control approach
A.
Change control approach
Answers
B.
Configuration item record
B.
Configuration item record
Answers
C.
Issue register
C.
Issue register
Answers
D.
Product status account
D.
Product status account
Answers
Suggested answer: B

Explanation:

The management product used to record relationships between specialist products in PRINCE2 is the Configuration Item Record. This record includes information on each product's status, version, and interrelationships, providing a comprehensive overview of how different project outputs are connected and managed.

Reference: PRINCE2 Foundation Manual

Which is a minimum requirement for applying the 'change' theme?

A.
Specify in the change control approach the means by which project products will be protected
A.
Specify in the change control approach the means by which project products will be protected
Answers
B.
Document the format and contents of the issue register
B.
Document the format and contents of the issue register
Answers
C.
Produce issue reports to document the impact assessment for requests for change
C.
Produce issue reports to document the impact assessment for requests for change
Answers
D.
Delegate the change authority to the senior supplier(s) for supplier off-specifications
D.
Delegate the change authority to the senior supplier(s) for supplier off-specifications
Answers
Suggested answer: B

Explanation:

A minimum requirement for applying the 'change' theme in PRINCE2 is to document the format and contents of the issue register. This ensures that all issues, including requests for change, are captured systematically and managed appropriately throughout the project lifecycle.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which action should the project manager take during the 'assessing issues' step?

A.
Create an exception plan tor project board approval
A.
Create an exception plan tor project board approval
Answers
B.
Gain project board feedback on the Issue priority
B.
Gain project board feedback on the Issue priority
Answers
C.
Consider the impact of alternative options for resolution
C.
Consider the impact of alternative options for resolution
Answers
D.
Determine the initial priority of the issue that has been raised
D.
Determine the initial priority of the issue that has been raised
Answers
Suggested answer: C

Explanation:

During the 'assessing issues' step, the project manager should consider the impact of alternative options for resolution. This involves evaluating different ways to address the issue, assessing their potential impacts on the project's objectives, timescales, costs, and risks, and then proposing the most appropriate solution for decision by the project board.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

A.
End stage report
A.
End stage report
Answers
B.
Checkpoint report
B.
Checkpoint report
Answers
C.
Highlight report
C.
Highlight report
Answers
D.
Exception report
D.
Exception report
Answers
Suggested answer: D

Explanation:

The Exception Report must be used to inform the project board of a predicted deviation from the agreed stage limits. This report is triggered when stage tolerances are forecasted to be exceeded, requiring the project board's decision on how to proceed with the project.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which control must be used as a minimum requirement for applying the 'progress' theme?

A.
A project plan
A.
A project plan
Answers
B.
Tolerances
B.
Tolerances
Answers
C.
An Issue register
C.
An Issue register
Answers
D.
Highlight reports
D.
Highlight reports
Answers
Suggested answer: B

Explanation:

Tolerances are a minimum requirement for applying the 'progress' theme in PRINCE2. They define the allowable deviations in time, cost, quality, scope, risk, and benefit objectives that do not require escalation to higher management levels. This control mechanism ensures that the project operates within agreed boundaries without frequent upper management intervention.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?

A.
Business case
A.
Business case
Answers
B.
Plans
B.
Plans
Answers
C.
Change
C.
Change
Answers
D.
Progress
D.
Progress
Answers
Suggested answer: D

Explanation:

The Progress theme in PRINCE2 establishes mechanisms to control the project against its baselines by providing ongoing forecasts for the project's objectives and continued viability. This theme ensures that the project remains on track to deliver the expected outcomes and can adapt to changes when necessary.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which management level should approve a course of action if project-level tolerance is exceeded?

A.
Corporate, programme management or the customer
A.
Corporate, programme management or the customer
Answers
B.
Project board
B.
Project board
Answers
C.
Project manager
C.
Project manager
Answers
D.
Team manager
D.
Team manager
Answers
Suggested answer: A

Explanation:

If project-level tolerance is exceeded, the course of action must be approved at a level higher than the project board, typically by corporate, programme management, or the customer. This ensures that higher management levels are involved in decisions when significant variances that might impact project viability or strategic alignment occur.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which describes a time-driven control?

A.
The dates for the project's end stage assessment included in the project plan
A.
The dates for the project's end stage assessment included in the project plan
Answers
B.
The expected frequency of progress reports specified in a work package
B.
The expected frequency of progress reports specified in a work package
Answers
C.
The expected dates for planned checks of specialist products included in a stage plan
C.
The expected dates for planned checks of specialist products included in a stage plan
Answers
D.
The planned exception assessment meeting to authorize a requested exception plan
D.
The planned exception assessment meeting to authorize a requested exception plan
Answers
Suggested answer: B

Explanation:

A time-driven control is defined as a monitoring system that is based on a fixed time interval, such as weekly or monthly progress reports. The expected frequency of progress reports specified in a work package represents a time-driven control, where updates are required at predefined intervals irrespective of the state of the project at those times.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which are purposes of the 'directing a project' process?

1. To enable the project board to be accountable for a project's success by making key decisions

2. To enable the project board to authorize work packages

3. To enable the project board to prepare the communication management approach

4. To enable the project board to exercise overall control of a project

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: D

Explanation:

The purposes of the 'directing a project' process are to enable the project board to be accountable for the project's success by making key decisions (1) and to exercise overall control of the project (4). This process ensures that strategic guidance and oversight are maintained, but does not directly involve the project board in authorizing work packages or preparing communication approaches---that's handled by the project manager.

Reference: = PRINCE2 7 Foundation handbook and online resources

Total 463 questions
Go to page: of 47