PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 33
List of questions
Related questions
Which activity is part of the recommended risk management procedure?
Which management product is used to record relationships between specialist products?
Which is a minimum requirement for applying the 'change' theme?
Which action should the project manager take during the 'assessing issues' step?
Which report must be used to inform the project board of a predicted deviation from agreed stage limits?
Which control must be used as a minimum requirement for applying the 'progress' theme?
Which theme establishes the mechanisms to control against baselines by providing a forecast for the project's objectives and continued viability?
Which management level should approve a course of action if project-level tolerance is exceeded?
Which describes a time-driven control?
Which are purposes of the 'directing a project' process?
1. To enable the project board to be accountable for a project's success by making key decisions
2. To enable the project board to authorize work packages
3. To enable the project board to prepare the communication management approach
4. To enable the project board to exercise overall control of a project
Question