Identify the missing word in the following sentence relating to one of the principles:

A PRINCE2 project should have [?] defined for each project objective.

A.
themes
A.
themes
Answers
B.
principles
B.
principles
Answers
C.
processes
C.
processes
Answers
D.
tolerances
D.
tolerances
Answers
Suggested answer: D

Explanation:

According to PRINCE2, a project should have tolerances defined for each project objective. Tolerances specify the permissible deviations in scope, time, cost, quality, risk, and benefits that are allowed before the deviation needs to be escalated to a higher authority. This is fundamental for the 'manage by exception' principle, allowing efficient use of time and resources by project management levels.

Reference: PRINCE2 Foundation Manual

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: B

Explanation:

The Communication Management Approach in PRINCE2 defines how information should be sent to interested parties and how often this information should be communicated. It includes details on the methods and frequency of communication necessary to engage stakeholders effectively and ensure that everyone who needs to be informed about the project has the right information at the right time.

Reference: PRINCE2 Foundation Manual

What is an advantage of dividing the project into stages?

A.
Detailed plans can be prepared closer to the time events will take place
A.
Detailed plans can be prepared closer to the time events will take place
Answers
B.
the project board can delegate management of the project to team managers
B.
the project board can delegate management of the project to team managers
Answers
C.
The project can be authorized by the project manager on a stage by stage basis
C.
The project can be authorized by the project manager on a stage by stage basis
Answers
D.
The project brief can be updated towards the end of each stage
D.
The project brief can be updated towards the end of each stage
Answers
Suggested answer: A

Explanation:

One of the advantages of dividing the project into stages, as advocated by PRINCE2, is that detailed plans can be prepared closer to the time events will take place. This allows planning to be based on more accurate, up-to-date information, improving the relevance and accuracy of the plans. This approach also allows for better response to changes and risks, as planning for later stages can adjust based on the outcomes and learnings from earlier stages.

Reference: PRINCE2 Foundation Manual

Which is a benefit of using PRINCE2?

A.
It promotes consistency of project work and the ability to reuse project assets.
A.
It promotes consistency of project work and the ability to reuse project assets.
Answers
B.
It includes techniques for critical path analysis and earned value analysis
B.
It includes techniques for critical path analysis and earned value analysis
Answers
C.
It enables a project manager to be accountable for the success of a project
C.
It enables a project manager to be accountable for the success of a project
Answers
D.
It prevents any changes once the scope of a project has been agreed
D.
It prevents any changes once the scope of a project has been agreed
Answers
Suggested answer: A

Explanation:

PRINCE2 benefits organizations and project management by promoting consistency across project work and facilitating the reuse of project assets. This includes methodologies, processes, and lessons learned which enhance efficiency and effectiveness in managing projects, thereby contributing to consistent project success and resource optimization.

Reference: = PRINCE2 7 Foundation handbook and online resources

How does the 'managing product delivery' process achieve its purpose?

A.
By agreeing requirements for how project work should be undertaken
A.
By agreeing requirements for how project work should be undertaken
Answers
B.
By producing highlight reports to enable the project board to oversee the work
B.
By producing highlight reports to enable the project board to oversee the work
Answers
C.
By requiring the project manager to produce and monitor team plans
C.
By requiring the project manager to produce and monitor team plans
Answers
D.
By escalating issues and risks that cannot be resolved within stage tolerance
D.
By escalating issues and risks that cannot be resolved within stage tolerance
Answers
Suggested answer: A

Explanation:

The 'Managing Product Delivery' process in PRINCE2 achieves its purpose by ensuring that the work required to deliver the project's products is agreed upon and conforms to the defined requirements. This process manages the link between the project manager and the team members by agreeing on assignments, ensuring that planned products are delivered to specifications, and that work progresses as planned.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

A.
Each party may have their own business case for undertaking the project
A.
Each party may have their own business case for undertaking the project
Answers
B.
Both parties must apply the same external governance to the project
B.
Both parties must apply the same external governance to the project
Answers
C.
The risk appetite should be collaboratively set before the project starts
C.
The risk appetite should be collaboratively set before the project starts
Answers
D.
Management systems need to be unified for successful project delivery
D.
Management systems need to be unified for successful project delivery
Answers
Suggested answer: A

Explanation:

In a commercial environment, it is common for each party involved in a project---namely the customer and suppliers---to have their own business case. This reflects their individual motives, expected benefits, and investment rationale for undertaking the project. Each party's business case addresses their specific strategic, commercial, and operational needs.

Reference: = PRINCE2 7 Foundation handbook and online resources

During the 'initiating a project' process, who specifies the required level of management control?

A.
Corporate, programme management or customer
A.
Corporate, programme management or customer
Answers
B.
Project board
B.
Project board
Answers
C.
Project manager
C.
Project manager
Answers
D.
Project assurance
D.
Project assurance
Answers
Suggested answer: B

Explanation:

During the 'Initiating a Project' process in PRINCE2, it is the responsibility of the project board to specify the required level of management control. This includes defining how the project will be managed, monitored, and controlled throughout its lifecycle. The project board ensures that the project remains viable and that management decisions are made with the appropriate level of oversight.

Reference: = PRINCE2 7 Foundation handbook and online resources

Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

A.
Project brief
A.
Project brief
Answers
B.
Project initiation documentation
B.
Project initiation documentation
Answers
C.
Project mandate
C.
Project mandate
Answers
D.
Project product description
D.
Project product description
Answers
Suggested answer: B

Explanation:

People who join a project after initiation can quickly and easily find comprehensive information about how the project is being managed in the Project Initiation Documentation (PID). The PID provides a detailed basis for the management of the project, including how the project is structured, governed, and what methods are being used. It is a central document that encapsulates all key information needed to understand the project management approach.

Reference: PRINCE2 Foundation Manual

Which is a minimum requirement when applying the 'risk' theme?

A.
To identity and ring-fence an explicit risk budget within the project's budget
A.
To identity and ring-fence an explicit risk budget within the project's budget
Answers
B.
To describe the probability impact grid in the risk management approach
B.
To describe the probability impact grid in the risk management approach
Answers
C.
To appoint project assurance to maintain the risk register during initiation
C.
To appoint project assurance to maintain the risk register during initiation
Answers
D.
To assess if risks might have a material impact on business justification
D.
To assess if risks might have a material impact on business justification
Answers
Suggested answer: D

Explanation:

One of the minimum requirements when applying the 'risk' theme in PRINCE2 is to assess whether risks could materially impact the business justification of the project. This assessment is crucial because it directly influences whether the project remains viable and worth continuing, in alignment with the continued business justification principle.

Reference: PRINCE2 Foundation Manual

What is a risk actionee responsible for?

A.
Identifying risks to the project that might occur in their department
A.
Identifying risks to the project that might occur in their department
Answers
B.
Owning and authorizing the use of the risk budget to fund risk responses
B.
Owning and authorizing the use of the risk budget to fund risk responses
Answers
C.
Managing, monitoring and controlling of all aspects of an assigned risk
C.
Managing, monitoring and controlling of all aspects of an assigned risk
Answers
D.
Carrying out a risk response action to respond to a particular risk
D.
Carrying out a risk response action to respond to a particular risk
Answers
Suggested answer: C

Explanation:

A risk actionee in PRINCE2 is responsible for managing, monitoring, and controlling all aspects of a specifically assigned risk. This role includes planning and implementing appropriate risk responses and ensuring that the risk is handled effectively throughout its lifecycle in the project.

Reference: PRINCE2 Foundation Manual