Identify the missing words in the following sentence.

The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

A.
project assurance
A.
project assurance
Answers
B.
the project board
B.
the project board
Answers
C.
the corporate, programme management or the customer
C.
the corporate, programme management or the customer
Answers
D.
a team manager
D.
a team manager
Answers
Suggested answer: D

Explanation:

The 'managing product delivery' process provides a controlled link between a team manager and the project manager. This process ensures that the work assigned to the team is authorized and managed according to the project's requirements, facilitating clear communication and effective delivery of project products.

Reference: = PRINCE2 7 Foundation handbook and online resources

Why does the project board review the PID during an end stage assessment?

A.
To confirm that project controls are adequate for the remainder of the project
A.
To confirm that project controls are adequate for the remainder of the project
Answers
B.
To notify the commissioning organization that the project has been authorized
B.
To notify the commissioning organization that the project has been authorized
Answers
C.
To review summarized progress to date and decide what to do next with the project
C.
To review summarized progress to date and decide what to do next with the project
Answers
D.
To ensure that post-project reviews of operational performance are planned
D.
To ensure that post-project reviews of operational performance are planned
Answers
Suggested answer: C

Explanation:

The project board reviews the Project Initiation Documentation (PID) during an end stage assessment primarily to review summarized progress to date and to decide the future course of action for the project. This review helps determine whether the project is still viable and if the project should continue into its next stage based on performance against the plan and the business case.

Reference: PRINCE2 Foundation Manual

Which is a purpose of the 'controlling a stage' process?

A.
To review the success of the project at the end of a management stage
A.
To review the success of the project at the end of a management stage
Answers
B.
To agree work package acceptance and delivery requirements
B.
To agree work package acceptance and delivery requirements
Answers
C.
To produce regular highlight reports for the project board
C.
To produce regular highlight reports for the project board
Answers
D.
To re-plan the current stage and the project when requested
D.
To re-plan the current stage and the project when requested
Answers
Suggested answer: C

Explanation:

The purpose of the 'controlling a stage' process in PRINCE2 is to ensure that the stage stays on course and reacts to unexpected events. Part of this process involves producing regular highlight reports for the project board, which summarizes the stage's progress, highlights any issues or risks, and keeps the board informed about ongoing activities.

Reference: PRINCE2 Foundation Manual

Which process provides information for the project board to review an updated project plan?

A.
Initiating a project
A.
Initiating a project
Answers
B.
Controlling a stage
B.
Controlling a stage
Answers
C.
Directing a project
C.
Directing a project
Answers
D.
Managing a stage boundary
D.
Managing a stage boundary
Answers
Suggested answer: D

Explanation:

The process that provides information for the project board to review an updated project plan is 'Managing a Stage Boundary'. This process involves preparing the information needed for the project board to review the current stage's performance, reassess the project viability, and make decisions regarding the next stage, including updates to the project plan if necessary.

Reference: PRINCE2 Foundation Manual

Which is a purpose of the 'initiating a project' process?

A.
To ensure the project has a sound basis before asking the project board to authorize the project
A.
To ensure the project has a sound basis before asking the project board to authorize the project
Answers
B.
To authorize the stage plan for the next management stage of the project
B.
To authorize the stage plan for the next management stage of the project
Answers
C.
To establish a contract between the project management team and the commissioning organization
C.
To establish a contract between the project management team and the commissioning organization
Answers
D.
To ensure that prerequisites are in place before starting the project
D.
To ensure that prerequisites are in place before starting the project
Answers
Suggested answer: A

Explanation:

The purpose of the 'Initiating a Project' process in PRINCE2 is to ensure that the project has a sound basis before the project board is asked to make any major commitment to the project. This process is crucial for establishing a stable foundation for the project, detailing the necessary aspects such as scope, timescales, costs, risks, and benefits before full-scale implementation commences.

Reference: PRINCE2 Foundation Manual

How should the 'managing a stage boundary' process be used towards the end of a project's final delivery stage?

A.
To plan the activities of the closing a project' process
A.
To plan the activities of the closing a project' process
Answers
B.
To implement any exception plan requests from the project board
B.
To implement any exception plan requests from the project board
Answers
C.
To create a benefits management approach for corporate, programme management or the customer
C.
To create a benefits management approach for corporate, programme management or the customer
Answers
D.
To review an issue received from a team manager
D.
To review an issue received from a team manager
Answers
Suggested answer: A

Explanation:

The 'Managing a Stage Boundary' process should be used towards the end of a project's final delivery stage to plan the activities of the 'Closing a Project' process. This includes preparing for the closure of the project by confirming project deliverables, ensuring all project work is completed and approved, and planning the activities that will ensure the project is formally closed and reviewed.

Reference: = PRINCE2 7 Foundation handbook and online resources

How often should the 'controlling a stage' process be used during a project?

A.
Once, for the whole project
A.
Once, for the whole project
Answers
B.
For each delivery stage in the project
B.
For each delivery stage in the project
Answers
C.
Whenever the project board meets
C.
Whenever the project board meets
Answers
D.
Twice, for initiation and for the rest of the project
D.
Twice, for initiation and for the rest of the project
Answers
Suggested answer: B

Explanation:

The 'Controlling a Stage' process should be used during each delivery stage of a project. This process is essential for the day-to-day management of the project stage by the project manager. It includes monitoring, reporting, and responding to issues within the stage to ensure the project remains within agreed tolerances.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which process is used by the project board to respond to on exception report?

A.
Controlling a stage
A.
Controlling a stage
Answers
B.
Managing a stage boundary
B.
Managing a stage boundary
Answers
C.
Managing product delivery
C.
Managing product delivery
Answers
D.
Directing a project
D.
Directing a project
Answers
Suggested answer: D

Explanation:

The 'Directing a Project' process is used by the project board to respond to an exception report. This process involves the project board making decisions on how to proceed when project tolerances are forecasted to be exceeded, which are typically communicated through an exception report.

Reference: = PRINCE2 7 Foundation handbook and online resources

When is the 'managing a stage boundary' process used?

A.
Immediately alter the project board has authorized the previous stage
A.
Immediately alter the project board has authorized the previous stage
Answers
B.
Immediately after the project board has authorized the next stage
B.
Immediately after the project board has authorized the next stage
Answers
C.
Near the end of each stage
C.
Near the end of each stage
Answers
D.
Near the end of delivery stages
D.
Near the end of delivery stages
Answers
Suggested answer: C

Explanation:

The 'Managing a Stage Boundary' process is used near the end of each stage of a project. This process includes the review of the current stage, preparation for the project board to authorize the next stage, updating a project plan, and, if necessary, updating the business case and project initiation documentation.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which statement describes the context of the 'initiating a project' process?

A.
The project is viewed from the perspective of the project board in this process
A.
The project is viewed from the perspective of the project board in this process
Answers
B.
This process should result in key stakeholders being committed to the project
B.
This process should result in key stakeholders being committed to the project
Answers
C.
This process is triggered by the assembly of the project brief
C.
This process is triggered by the assembly of the project brief
Answers
D.
The 'controlling a stage' process will start immediately after this process
D.
The 'controlling a stage' process will start immediately after this process
Answers
Suggested answer: A

Explanation:

During the 'Initiating a Project' process in PRINCE2, the project is considered from the perspective of the project board. This process ensures that the project board has all the necessary information to commit to the project, understanding its scope, timescales, costs, risks, and overall approach before granting formal approval to proceed.

Reference: PRINCE2 Foundation Manual