Which term is defined as a product that will not meet is quality specifications?

A.
Off-specification
A.
Off-specification
Answers
B.
Request for change
B.
Request for change
Answers
C.
Concern
C.
Concern
Answers
D.
Problem
D.
Problem
Answers
Suggested answer: A

Explanation:

The term 'off-specification' is defined as a product that will not meet its quality specifications. This indicates a variance from what was agreed upon in the product description, requiring attention and potentially corrective action to ensure the project's outputs meet the required standards.

Reference: PRINCE2 Foundation glossary and project documentation guidelines.

The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?

A.
issue register
A.
issue register
Answers
B.
issue report
B.
issue report
Answers
C.
Issue management approach
C.
Issue management approach
Answers
D.
Risk management approach
D.
Risk management approach
Answers
Suggested answer: A

Explanation:

The project manager should review the 'issue register' to know what modifications have been proposed to an approved product during the stage. The issue register records all issues that may impact the project, including requests for change, concerns, and off-specifications, providing an overview of current and potential problems affecting project products.

Reference: PRINCE2 Foundation training materials and issue management guidance.

Which control is time-driven?

A.
The creation of a highlight report
A.
The creation of a highlight report
Answers
B.
The completion of the PID
B.
The completion of the PID
Answers
C.
The creation of an exception report
C.
The creation of an exception report
Answers
D.
The end of the financial year
D.
The end of the financial year
Answers
Suggested answer: A

Explanation:

In PRINCE2, the creation of a highlight report is a time-driven control, typically scheduled at regular intervals, such as weekly or monthly during a stage. This report provides the Project Board and other stakeholders with a summary of the stage status, and it is triggered by the passage of time, not by specific events or exceptions within the project.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Which process should be Used to confirm that the project continues to deliver against the strategic objectives?

A.
Managing a stage boundary
A.
Managing a stage boundary
Answers
B.
Managing product delivery
B.
Managing product delivery
Answers
C.
Initiating a project
C.
Initiating a project
Answers
D.
Closing a project
D.
Closing a project
Answers
Suggested answer: A

Explanation:

The 'Managing a Stage Boundary' process in PRINCE2 is designed to confirm that the project remains viable and continues to align with organizational strategic objectives. This process involves reviewing the project's performance, updating the project plan, and reconfirming the business case to ensure that the project continues to deliver value as expected.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Which is the definition of a requirement?

A.
A need or expectation that has been documented in an approved management product
A.
A need or expectation that has been documented in an approved management product
Answers
B.
An event relevant to the project that requires project management consideration
B.
An event relevant to the project that requires project management consideration
Answers
C.
A prediction about future performance made by studying historical data and past patterns
C.
A prediction about future performance made by studying historical data and past patterns
Answers
D.
An uncertain event that, should it occur, will have an effect on the project.
D.
An uncertain event that, should it occur, will have an effect on the project.
Answers
Suggested answer: A

Explanation:

A requirement in the context of PRINCE2 is defined as a documented need or expectation that is formally approved and used as a basis for further project development. This documentation typically includes specific details about project scope, expected outcomes, and performance criteria, which are crucial for project planning and execution.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.

Which principle is the project board applying?

A.
Manage by exception
A.
Manage by exception
Answers
B.
Manage by stages
B.
Manage by stages
Answers
C.
Ensure continued business Justification
C.
Ensure continued business Justification
Answers
D.
Focus on products
D.
Focus on products
Answers
Suggested answer: C

Explanation:

The principle of 'Ensure continued business justification' in PRINCE2 requires that the project remains justified throughout its lifecycle. By reviewing the benefits management approach to ensure it includes sufficient benefit reviews after the project's closure, the project board is applying this principle to confirm that the project continues to provide value and that its benefits are realized as planned, even post-project.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

What is a purpose of the 'quality' practice?

A.
To predict whether the project will deliver on time and to cost and whether the benefits will outweigh the costs
A.
To predict whether the project will deliver on time and to cost and whether the benefits will outweigh the costs
Answers
B.
To resolve off-specifications, that are Identified during the project, at the end of the project
B.
To resolve off-specifications, that are Identified during the project, at the end of the project
Answers
C.
To plan the project so that there is time to deal with quality defects late in the project
C.
To plan the project so that there is time to deal with quality defects late in the project
Answers
D.
To identify the user's expectations and determine how the project will achieve them
D.
To identify the user's expectations and determine how the project will achieve them
Answers
Suggested answer: C

Explanation:

The project manager needs to prioritize several criteria that the project product must meet for acceptance during the step of 'Describing the quality management approach'. This step involves defining how quality will be managed throughout the project, ensuring that all quality criteria are clearly identified, prioritized, and agreed upon by stakeholders.

Reference: PRINCE2 Foundation manual and quality management technique guidelines.

The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the 'quality management technique should this occur?

A.
Gathering user inputs
A.
Gathering user inputs
Answers
B.
Accepting products
B.
Accepting products
Answers
C.
Describing the quality management approach
C.
Describing the quality management approach
Answers
D.
controlling quality
D.
controlling quality
Answers
Suggested answer: C

Which management product Soul guide the Project management team on how to manage multiple aspects of the project?

A.
Project initiation documentation
A.
Project initiation documentation
Answers
B.
Project plan
B.
Project plan
Answers
C.
Business case
C.
Business case
Answers
D.
Exception plan
D.
Exception plan
Answers
Suggested answer: A

Explanation:

The Project Initiation Documentation (PID) should guide the project management team on how to manage multiple aspects of the project. It is a key management product that includes crucial information like the project's definition, approach to management, and controls. It serves as the baseline document for managing the project's scope, quality, costs, timescales, risk, and benefits.

Reference: PRINCE2 Foundation official guide and project management documentation resources.

Which is definition of culture?

A.
The set of shared attitudes, values, goals, and ways of working that characterize a group of people
A.
The set of shared attitudes, values, goals, and ways of working that characterize a group of people
Answers
B.
The process when people from across the project ecosystem work together
B.
The process when people from across the project ecosystem work together
Answers
C.
An essential aspect of project management that needs to be continually addressed
C.
An essential aspect of project management that needs to be continually addressed
Answers
D.
The tailoring required to take into account the complexity or simplicity of a project
D.
The tailoring required to take into account the complexity or simplicity of a project
Answers
Suggested answer: A

Explanation:

The definition of 'culture' in the context of PRINCE2 and project management is the set of shared attitudes, values, goals, and ways of working that characterize a group of people. Culture impacts how project teams operate and interact, influencing decision-making, teamwork, and the overall success of a project.