Which team is defined as motivating people to achieve a project's objectives?

A.
Leadership
A.
Leadership
Answers
B.
Management
B.
Management
Answers
C.
Quality assurance
C.
Quality assurance
Answers
D.
Co-creation
D.
Co-creation
Answers
Suggested answer: A

Explanation:

The term 'Leadership' best describes the team role defined as motivating people to achieve a project's objectives. Leadership involves guiding, inspiring, and encouraging the project team to meet the project goals and to overcome challenges throughout the project lifecycle.

Reference: PRINCE2 Foundation training materials and leadership roles overview.

How is Uncertainty Identified, assessed and controlled?

A.
By avoiding or reducing a threat
A.
By avoiding or reducing a threat
Answers
B.
By analysing the risk cause in detail
B.
By analysing the risk cause in detail
Answers
C.
By applying the risk practice
C.
By applying the risk practice
Answers
D.
By allocating a risk budget to the project
D.
By allocating a risk budget to the project
Answers
Suggested answer: C

Explanation:

Uncertainty in a project is identified, assessed, and controlled by applying the risk practice. This practice involves systematic risk identification, analysis, and management, ensuring that risks are properly understood and addressed through appropriate responses to protect the project objectives.

Reference: PRINCE2 Foundation official guide and risk management section.

What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?

A.
A project
A.
A project
Answers
B.
A baselined product
B.
A baselined product
Answers
C.
The project scope
C.
The project scope
Answers
D.
The business
D.
The business
Answers
Suggested answer: A

Explanation:

A project is defined as a temporary organization that is created for the purpose of delivering business products according to an agreed business case. This definition emphasizes the temporary and purpose-driven nature of a project, which is organized to achieve specific business objectives and then disbanded upon achieving its goals.

Reference: PRINCE2 7 Foundation manual and basic project management concepts.

In which process are the key decisions to control the project made?

A.
Directing a project
A.
Directing a project
Answers
B.
Initiating a project
B.
Initiating a project
Answers
C.
Managing a stage boundary
C.
Managing a stage boundary
Answers
D.
Controlling a stage
D.
Controlling a stage
Answers
Suggested answer: A

Explanation:

In PRINCE2, the 'Directing a Project' process is where the key decisions to control the overall project are made. This process involves the Project Board and is crucial for providing overall direction and management oversight throughout the lifecycle of the project, including key decision points such as project initiation, stage boundaries, and project closure.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

Which TWO are objectives of the 'starting up a project' process?

1. To create a common view of How the required quality will be achieved

2.To give authority to initiate the project

3. To appoint the resources needed to do the work to initiate the project

4. To ensure that projects are initiated based or agreed acceptance criteria for the project product.

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: B

Explanation:

The objectives of the 'Starting up a Project' process in PRINCE2 include giving authority to initiate the project (ensuring there is a solid foundation before significant expenditure is committed), and appointing the resources needed to undertake the initiation phase of the project. This process sets the project up for success by confirming its scope, defining how it will be managed, and allocating the necessary resources.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

How is uncertainty identified, assessed and controlled?

A.
By avoiding or reducing a threat
A.
By avoiding or reducing a threat
Answers
B.
By analysing the risk cause in detail
B.
By analysing the risk cause in detail
Answers
C.
By applying the risk practice
C.
By applying the risk practice
Answers
D.
By allocating a risk budget to the project
D.
By allocating a risk budget to the project
Answers
Suggested answer: C

Explanation:

Uncertainty in a project is identified, assessed, and controlled through the application of the 'Risk Management Practice' in PRINCE2. This practice involves systematic risk identification, assessment, and response planning to manage project risks effectively and ensure that they are within acceptable tolerance levels.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

What is a description of a leadership activity within a project?

A.
Understanding and working with different departments outside of the project team
A.
Understanding and working with different departments outside of the project team
Answers
B.
Agreeing a work package with a tear manager to deliver products using specific tools
B.
Agreeing a work package with a tear manager to deliver products using specific tools
Answers
C.
Ensuring that a co-located project team uses the agreed communication methods
C.
Ensuring that a co-located project team uses the agreed communication methods
Answers
D.
Creating a stage plan and product descriptions for the products to be created in the next stage
D.
Creating a stage plan and product descriptions for the products to be created in the next stage
Answers
Suggested answer: A

Explanation:

A key leadership activity within a project involves understanding and effectively working with different departments outside of the project team. This includes managing stakeholder expectations, ensuring alignment with broader organizational goals, and facilitating cross-functional collaboration, which are essential for the successful delivery of project outcomes.

Reference: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation

The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

In which process should the project manager define this information?

A.
Starting up a project
A.
Starting up a project
Answers
B.
Initiating a project
B.
Initiating a project
Answers
C.
Directing a project
C.
Directing a project
Answers
D.
Managing a stage boundary
D.
Managing a stage boundary
Answers
Suggested answer: B

Explanation:

During the 'Initiating a Project' process, the project manager develops key information, including the detailed Project Initiation Documentation (PID), which enables the project board to decide whether to proceed with the project. This information outlines the approach, plans, and controls that will govern the project, providing a foundation for detailed planning and informed decision-making by the project board.

Reference: PRINCE2 7 Foundation materials on the 'Initiating a Project' process.

The project manager reviews the project product description to identify the detailed requirement for each product.

In which step of the quality management technique should the project manager do this review?

A.
Gathering user inputs
A.
Gathering user inputs
Answers
B.
Accepting products ay
B.
Accepting products ay
Answers
C.
Describing the quality management approach
C.
Describing the quality management approach
Answers
D.
Controlling quality
D.
Controlling quality
Answers
Suggested answer: A

Explanation:

Reviewing the project product description to identify detailed requirements for each product aligns with the step of 'Describing the Quality Management Approach' in the quality management technique. This step involves defining how quality will be managed and controlled throughout the project, ensuring that all product requirements are understood and planned for in accordance with the project's quality expectations.

Reference: PRINCE2 7 Foundation guide on quality management.

Which feature of a stage plan suggests that a project is in danger of scope creep?

A.
Stage plans are prepared by the project manager as the stage comes to an end
A.
Stage plans are prepared by the project manager as the stage comes to an end
Answers
B.
Products identified in a stage plan cannot be traced back to the project plan
B.
Products identified in a stage plan cannot be traced back to the project plan
Answers
C.
The team delivering the stage plan includes staff from different parts of an organization
C.
The team delivering the stage plan includes staff from different parts of an organization
Answers
D.
it is not possible to implement remedial actions for an exception by updating a stage plan
D.
it is not possible to implement remedial actions for an exception by updating a stage plan
Answers
Suggested answer: B

Explanation:

A feature of a stage plan that suggests a project is in danger of scope creep is when products identified in the stage plan cannot be traced back to the project plan. This indicates a lack of alignment between the stage and overall project objectives, potentially leading to uncontrolled changes or additions to the project scope, known as scope creep.

Reference: PRINCE2 7 Foundation documentation on stage planning and scope management.

Total 463 questions
Go to page: of 47