Which is an assumption about the PRINCE2 customer/supplier environment?

A.
The supplier will pay for the project
A.
The supplier will pay for the project
Answers
B.
The customer will provide the resources to deliver the products
B.
The customer will provide the resources to deliver the products
Answers
C.
The customer will specify the desired result
C.
The customer will specify the desired result
Answers
D.
The supplier will tailor the project's application of PRINCE2
D.
The supplier will tailor the project's application of PRINCE2
Answers
Suggested answer: C

Explanation:

A fundamental assumption in the PRINCE2 framework regarding the customer/supplier environment is that the customer will specify the desired result. This assumption underlines the relationship where the customer defines what they want to achieve from the project, and the supplier provides the resources and expertise to deliver the project's outputs that meet these specifications.

Reference: PRINCE2 Foundation Manual

Which is a purpose of the 'directing a project' process?

A.
To create and authorize the project mandate
A.
To create and authorize the project mandate
Answers
B.
To ensure that work on products allocated to the team is authorized and agreed
B.
To ensure that work on products allocated to the team is authorized and agreed
Answers
C.
To control the day-to-day running of the project
C.
To control the day-to-day running of the project
Answers
D.
To delegate day-to-day management of the project to the project manager
D.
To delegate day-to-day management of the project to the project manager
Answers
Suggested answer: D

Explanation:

The purpose of the 'Directing a Project' process in PRINCE2 is to enable the project board to be accountable for the project's success by making key decisions and exercising overall control while delegating the day-to-day management of the project to the project manager. This includes the authority to initiate and close the project, deliver stage boundaries, and be updated on project progress.

Reference: = PRINCE2 7 Foundation handbook and online resources

Who are considered as the stakeholders in a project?

A.
Only those benefitting the project
A.
Only those benefitting the project
Answers
B.
Everyone in the corporate organization
B.
Everyone in the corporate organization
Answers
C.
Everyone involved in or affected by the project
C.
Everyone involved in or affected by the project
Answers
D.
Only those who are users of the products
D.
Only those who are users of the products
Answers
Suggested answer: C

Explanation:

In PRINCE2, stakeholders of a project are defined as all individuals or groups that are either involved in, affected by, or can affect the project's outcomes. This broad definition ensures that the project management considers all relevant perspectives and interests, which can impact the project's success.

Reference: = PRINCE2 7 Foundation handbook and online resources

What is the result of the change derived from using the project's product?

A.
Benefit
A.
Benefit
Answers
B.
Dis-benefit
B.
Dis-benefit
Answers
C.
Outcome
C.
Outcome
Answers
D.
Output
D.
Output
Answers
Suggested answer: C

Explanation:

The result of the change derived from using the project's product is referred to as the 'outcome'. An outcome is the effect of the change, typically a new capability that the project's outputs enable within the organization. This differs from outputs (which are tangible deliverables of the project) and benefits (which are the measurable improvements resulting from an outcome).

Reference: = PRINCE2 7 Foundation handbook and online resources

According to the 'continued business justification' principle, what should happen to the funds when a project can no longer be justified?

A.
They should be returned to corporate, programme management or customer
A.
They should be returned to corporate, programme management or customer
Answers
B.
They should be used to create an alternative business case for the project
B.
They should be used to create an alternative business case for the project
Answers
C.
They should be transferred back to the project board to reassign
C.
They should be transferred back to the project board to reassign
Answers
D.
They should be used to deliver a reduction in the scope of the project
D.
They should be used to deliver a reduction in the scope of the project
Answers
Suggested answer: A

Explanation:

According to the 'continued business justification' principle of PRINCE2, if a project can no longer be justified --- meaning it no longer meets its original or updated justification for a viable return on investment --- the funds allocated to it should be returned to corporate, programme management, or the customer. This ensures that resources are not wasted on unjustifiable projects.

Reference: = PRINCE2 7 Foundation handbook and online resources

How are team managers involved in tailoring PRINCE2 suit the project?

A.
Team managers are accountable for the tailoring of the work packages
A.
Team managers are accountable for the tailoring of the work packages
Answers
B.
Team managers may advice on tailoring to improve the management of work packages
B.
Team managers may advice on tailoring to improve the management of work packages
Answers
C.
Team managers should not be involved in tailoring PRINCE2
C.
Team managers should not be involved in tailoring PRINCE2
Answers
D.
Team managers should document the tailoring of the work packages
D.
Team managers should document the tailoring of the work packages
Answers
Suggested answer: B

Explanation:

While team managers in PRINCE2 are primarily responsible for the production of the work packages assigned to them, they may also provide valuable advice on tailoring the methodology to better manage these work packages within the specific context of the project. Their practical experience and direct involvement with project delivery can offer insights into how PRINCE2 can be adapted to enhance efficiency and effectiveness at the team level.

Reference: PRINCE2 Foundation Manual

=========================

How does the 'managing product delivery' process ensure that the team manager's perspective is provided in a work package?

A.
The work packages are defined by the team manager and supported by a team plan
A.
The work packages are defined by the team manager and supported by a team plan
Answers
B.
the work packages provided by the project manager are agreed by the team manager
B.
the work packages provided by the project manager are agreed by the team manager
Answers
C.
The team plans are checked by project assurance against the work packages
C.
The team plans are checked by project assurance against the work packages
Answers
D.
The stage plan covering the work packages is created with input from the team manager
D.
The stage plan covering the work packages is created with input from the team manager
Answers
Suggested answer: B

Explanation:

In the 'Managing Product Delivery' process of PRINCE2, the team manager's perspective is considered by ensuring that work packages provided by the Project Manager are agreed upon by the Team Manager. This agreement includes understanding the requirements, scope, and criteria of the work packages, thus ensuring that the team manager is fully informed and agrees with what needs to be delivered.

Reference: PRINCE2 Foundation Manual

What must be produced to meet the minimum requirements when applying the change theme?

A.
A change budget for the analysis of change
A.
A change budget for the analysis of change
Answers
B.
Records of the decisions made on all issues
B.
Records of the decisions made on all issues
Answers
C.
Documents recording the version of each product
C.
Documents recording the version of each product
Answers
D.
Status reports on all products being produced
D.
Status reports on all products being produced
Answers
Suggested answer: B

Explanation:

To meet the minimum requirements when applying the change theme in PRINCE2, it is necessary to maintain records of the decisions made on all issues. This includes documenting how each issue was addressed and any subsequent changes made to project plans or products. This record-keeping is crucial for traceability, accountability, and ensuring that decisions are aligned with project objectives and governance.

Reference: PRINCE2 Foundation Manual

Which are reasons for a benefits management approach?

1. To state how improvements will be measured

2. To confirm that the benefits are realized

3. To estimate the costs of improvement

4. To define the reason for delivering the improvement

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: D

Explanation:

The Benefits Management Approach in PRINCE2 is designed to outline how and when the improvements (benefits) delivered by the project will be measured and to define the reason for delivering these improvements. This approach ensures that there is a clear understanding of the project's intended outcomes and how these will contribute to the organization's objectives, thereby justifying the project's existence and ongoing investment.

Reference: PRINCE2 Foundation Manual

Which is a purpose of the quality theme?

A.
To establish how the project will ensure that all products created meet their requirements
A.
To establish how the project will ensure that all products created meet their requirements
Answers
B.
To establish baselines against which any changes to products can be assessed
B.
To establish baselines against which any changes to products can be assessed
Answers
C.
To identify all the products of the project to ensure the scope has been adequately defined
C.
To identify all the products of the project to ensure the scope has been adequately defined
Answers
D.
To determine the communication needs of the organization's quality assurance function
D.
To determine the communication needs of the organization's quality assurance function
Answers
Suggested answer: A

Explanation:

The purpose of the quality theme in PRINCE2 is to define and implement the means by which the project will ensure that all products are fit for purpose and meet their requirements. This theme is essential for planning, designing, developing, and delivering products that satisfy the customer's expectations and standards defined for the project.

Reference: = PRINCE2 7 Foundation handbook and online resources

Total 463 questions