Why is it necessary to apply the 'defined roles and responsibilities' principle?

A.
Because the people involved in a project should know what is expected of them
A.
Because the people involved in a project should know what is expected of them
Answers
B.
Because the project management team should be cross-functional
B.
Because the project management team should be cross-functional
Answers
C.
Because the user and supplier interests should be involved on a need-to-know basis
C.
Because the user and supplier interests should be involved on a need-to-know basis
Answers
D.
Because the project manager should represent all the stakeholders of the project
D.
Because the project manager should represent all the stakeholders of the project
Answers
Suggested answer: A

Explanation:

The 'defined roles and responsibilities' principle in PRINCE2 is essential because it ensures clarity and efficiency in project management. By clearly defining roles and responsibilities, everyone involved in the project understands their tasks, responsibilities, and reporting relationships. This clarity helps in reducing confusion and improving communication and accountability among project team members.

Reference: PRINCE2 Foundation Manual

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

A.
After the executive has been appointed
A.
After the executive has been appointed
Answers
B.
When authorized by the corporate, programme management or the customer
B.
When authorized by the corporate, programme management or the customer
Answers
C.
Before work to start the project commences
C.
Before work to start the project commences
Answers
D.
When an organization produces its business plans
D.
When an organization produces its business plans
Answers
Suggested answer: C

Explanation:

According to the 'continued business justification' principle in PRINCE2, a justifiable reason for a project is required before any work to start the project begins. This ensures that projects are initiated only when there is a clear business need, aligned with organizational objectives, and there is an expectation of value creation. The business case is developed during the initial stages of the project and is maintained and reviewed throughout the project lifecycle.

Reference: PRINCE2 Foundation Manual

What is the change authority role permitted to authorize?

A.
Risks to the project
A.
Risks to the project
Answers
B.
Adjustments to the limits on the change budget
B.
Adjustments to the limits on the change budget
Answers
C.
Changes to stage tolerance
C.
Changes to stage tolerance
Answers
D.
Changes to the project that do not exceed a defined budget
D.
Changes to the project that do not exceed a defined budget
Answers
Suggested answer: D

Explanation:

The role of the change authority in PRINCE2 is to authorize changes within the project that do not exceed a predefined budget. This role is designated to ensure that any change proposals are evaluated and approved without exceeding the allocated budget for changes, thereby maintaining control over project costs and scope.

Reference: PRINCE2 Foundation Manual

Which is a minimum requirement for applying the change theme?

A.
To identify whether an issue affects the continuation of the project
A.
To identify whether an issue affects the continuation of the project
Answers
B.
To ensure each change is managed as an exception
B.
To ensure each change is managed as an exception
Answers
C.
To produce a breakdown of the products to be produced
C.
To produce a breakdown of the products to be produced
Answers
D.
To tailor all changes to improve the quality of the project
D.
To tailor all changes to improve the quality of the project
Answers
Suggested answer: A

Explanation:

A minimum requirement for applying the change theme in PRINCE2 is to identify whether an issue has the potential to affect the continuation of the project. This involves assessing the impact of potential changes or issues on the project's objectives and deciding whether they warrant considering the project as unviable in its current form.

Reference: = PRINCE2 7 Foundation handbook and online resources

Identify the missing words in the following sentence.

The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

A.
benefits, change, risk,
A.
benefits, change, risk,
Answers
B.
benefits, quality, risk,
B.
benefits, quality, risk,
Answers
C.
change, quality, risk,
C.
change, quality, risk,
Answers
D.
benefits, change, quality,
D.
benefits, change, quality,
Answers
Suggested answer: B

Explanation:

The six aspects of project performance to be managed, as outlined in PRINCE2, are benefits, costs, timescales, scope, quality, and risk. Managing these aspects helps ensure that the project delivers its intended outputs while adhering to predetermined constraints and achieving desired outcomes.

Reference: = PRINCE2 7 Foundation handbook and online resources

Which is a purpose of the quality theme?

A.
To check that the project is viable and achievable
A.
To check that the project is viable and achievable
Answers
B.
To ensure that the project outputs are agreed
B.
To ensure that the project outputs are agreed
Answers
C.
To ensure that formal issues are recorded
C.
To ensure that formal issues are recorded
Answers
D.
To enable the project to be managed according to plan
D.
To enable the project to be managed according to plan
Answers
Suggested answer: B

Explanation:

The purpose of the quality theme in PRINCE2 is to ensure that the project outputs meet the requirements that have been agreed upon. This theme guides the processes and activities required to verify that deliverables are fit for purpose and meet the standards expected by stakeholders.

Reference: = PRINCE2 7 Foundation handbook and online resources

What should the benefits management approach define?

A.
What actions will be taken to ensure the project's outcomes are achieved
A.
What actions will be taken to ensure the project's outcomes are achieved
Answers
B.
What will be used to record the effectiveness of the project's approaches
B.
What will be used to record the effectiveness of the project's approaches
Answers
C.
How the project has progressed against its plans
C.
How the project has progressed against its plans
Answers
D.
The suitability of the project management team structure
D.
The suitability of the project management team structure
Answers
Suggested answer: A

Explanation:

The Benefits Management Approach in PRINCE2 defines the specific actions that will be taken to ensure the project's outcomes are achieved. This approach includes plans for realizing benefits both during and after the project's lifecycle, ensuring that the project delivers the expected value to its stakeholders.

Reference: = PRINCE2 7 Foundation handbook and online resources

Who is responsible for documenting any tailoring of the business case theme?

A.
Executive
A.
Executive
Answers
B.
Business project assurance
B.
Business project assurance
Answers
C.
Project manager
C.
Project manager
Answers
D.
Corporate management
D.
Corporate management
Answers
Suggested answer: C

Explanation:

In PRINCE2, the responsibility for documenting any tailoring of the Business Case theme, along with other themes, generally falls to the Project Manager. This includes documenting how the theme is being applied in a particular project context, ensuring the approach remains appropriate and meets the project's requirements.

Reference: PRINCE2 Foundation Manual

Identify the missing word(s) in the following sentence.

The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

A.
delivery step
A.
delivery step
Answers
B.
benefit
B.
benefit
Answers
C.
delivery stage
C.
delivery stage
Answers
D.
team plan
D.
team plan
Answers
Suggested answer: C

Explanation:

The 'Controlling a Stage' process in PRINCE2 is used to manage and control each 'delivery stage' of a project. This process focuses on the day-to-day management of the project stages, ensuring that the project remains within its agreed tolerances and effectively addressing issues as they arise.

Reference: PRINCE2 Foundation Manual

What is documented in the project plan to support the 'manage by exception' principle?

A.
The project's tolerances for cost and time
A.
The project's tolerances for cost and time
Answers
B.
A project product's quality criteria
B.
A project product's quality criteria
Answers
C.
The expected project benefits
C.
The expected project benefits
Answers
D.
Activities to mitigate project risks
D.
Activities to mitigate project risks
Answers
Suggested answer: A

Explanation:

In support of the 'manage by exception' principle, the Project Plan in PRINCE2 documents the project's tolerances for key variables such as cost, time, quality, scope, risk, and benefit. These tolerances define the limits within which the Project Manager can operate without needing to escalate decisions to the Project Board, facilitating efficient decision-making and control at each level of project management.

Reference: PRINCE2 Foundation Manual