ExamGecko
Home / PRINCE2 / PRINCE2-7-Foundation / List of questions
Ask Question

PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 13

List of questions

Question 121

Report Export Collapse

Which statement about the quality review technique is FALSE?

It enables a check to be made on a product's fitness for purpose
It enables a check to be made on a product's fitness for purpose
It defines the quality responsibilities of the project team
It defines the quality responsibilities of the project team
It supports the management of future changes by providing a baseline for a product
It supports the management of future changes by providing a baseline for a product
It is used to gain wider acceptance of a product by involving key interested parties
It is used to gain wider acceptance of a product by involving key interested parties
Suggested answer: B
Explanation:

The statement that the quality review technique defines the quality responsibilities of the project team is false. The quality review technique in PRINCE2 primarily focuses on checking the product's fitness for purpose, involving key parties to gain wider acceptance, and providing a baseline to manage future changes, but does not specifically define the quality responsibilities of the team.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Nicholas Roy
51 questions

Question 122

Report Export Collapse

Which is part of quality control?

Undertake quality reviews
Undertake quality reviews
Write Product Descriptions
Write Product Descriptions
Provide assurance that the project is being conducted properly
Provide assurance that the project is being conducted properly
Document the customer's quality expectations
Document the customer's quality expectations
Suggested answer: A
Explanation:

Undertaking quality reviews is a part of quality control within the PRINCE2 methodology. Quality control involves checking products against requirements and standards through activities like reviews, tests, and evaluations to ensure they meet the expected quality levels.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Kayode Omotosho
46 questions

Question 123

Report Export Collapse

Which is part of quality control?

Document the project's acceptance criteria in the Project Product Description
Document the project's acceptance criteria in the Project Product Description
Define the quality responsibilities of those involved in the production of the products
Define the quality responsibilities of those involved in the production of the products
Produce quality records to show that the planned quality activities have been carried out
Produce quality records to show that the planned quality activities have been carried out
Maintain the corporate organization's quality management system
Maintain the corporate organization's quality management system
Suggested answer: C
Explanation:

Producing quality records is a key part of quality control in PRINCE2. These records provide documented evidence that quality activities have been planned and executed according to the project's quality requirements, helping to ensure transparency and accountability in the quality management process.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Okan YILDIZ
45 questions

Question 124

Report Export Collapse

Which of the following statements about customer's quality expectations and acceptance criteria are true?

1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.

2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

Only 1 is true
Only 1 is true
Only 2 is true
Only 2 is true
Both 1 and 2 are true
Both 1 and 2 are true
Neither 1 or 2 are true
Neither 1 or 2 are true
Suggested answer: B
Explanation:

In PRINCE2, customer's quality expectations (CQEs) are a high-level statement of what the customer expects from the project and are often expressed in broad terms. They are not necessarily measurable on their own but provide a sense of general quality requirements. In contrast, acceptance criteria are specific and precise; they form the list of conditions that a project product must meet to be accepted by key stakeholders. Therefore, statement 1 is false, and statement 2 correctly describes the customer's quality expectations.

Reference: PRINCE2 7 Foundation handbook and official documents.

asked 23/09/2024
Gajendran Balasingam
43 questions

Question 125

Report Export Collapse

Which is a true statement about acceptance criteria?

Acceptance criteria are used to produce the customer's quality expectations
Acceptance criteria are used to produce the customer's quality expectations
Acceptance criteria are less specific and precise than customer's quality expectations
Acceptance criteria are less specific and precise than customer's quality expectations
Once agreed, acceptance criteria CANNOT be changed
Once agreed, acceptance criteria CANNOT be changed
Acceptance criteria should be agreed between the customer and the supplier
Acceptance criteria should be agreed between the customer and the supplier
Suggested answer: D
Explanation:

Acceptance criteria should indeed be agreed upon between the customer and the supplier. This ensures that there is a clear, shared understanding of the conditions under which project outputs will be accepted. Acceptance criteria are detailed and measurable, contrary to being less specific than the customer's quality expectations. They can also be modified if necessary, provided there is agreement from relevant stakeholders.

Reference: PRINCE2 7 Foundation resources and materials.

asked 23/09/2024
Vishal Sahare
51 questions

Question 126

Report Export Collapse

Which is a responsibility of a risk owner?

Identify risks to the project that might occur in their department
Identify risks to the project that might occur in their department
Own and authorize the use of the risk budget to fund risk responses
Own and authorize the use of the risk budget to fund risk responses
Manage, monitor and control all aspects of an assigned risk
Manage, monitor and control all aspects of an assigned risk
Determine project risk appetite
Determine project risk appetite
Suggested answer: C
Explanation:

The responsibility of a risk owner in PRINCE2 involves managing, monitoring, and controlling all aspects of the risk they are assigned. This includes ensuring appropriate risk responses are planned and implemented effectively.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Cihad Yorulmaz
32 questions

Question 127

Report Export Collapse

Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

Project Assurance
Project Assurance
Project Support
Project Support
the risk actionee
the risk actionee
the risk owner
the risk owner
Suggested answer: C
Explanation:

In PRINCE2, the role specifically responsible for carrying out risk response actions is referred to as the 'risk actionee'. This role is assigned to an individual who is tasked with implementing the agreed upon actions to address specific risks. The risk owner, on the other hand, is responsible for the overall management of the risk.

Reference: PRINCE2 7 Foundation handbook and official documents.

asked 23/09/2024
Michael Crowson
50 questions

Question 128

Report Export Collapse

Which is a purpose of the Risk theme?

Establish a method for the implementation of continuous improvement during the project
Establish a method for the implementation of continuous improvement during the project
Identify, assess and control problems that have occurred
Identify, assess and control problems that have occurred
Provide the Project Board with a time-driven control to capture all project risks
Provide the Project Board with a time-driven control to capture all project risks
Establish a cost-effective procedure to identify, assess and control risks
Establish a cost-effective procedure to identify, assess and control risks
Suggested answer: D
Explanation:

The purpose of the Risk theme in PRINCE2 is to establish a cost-effective procedure to identify, assess, and control uncertainties or risks. This ensures that the project can cope with risks effectively. The Risk theme supports decision-making by improving the understanding of risks and their likely impact on achieving the project's objectives.

Reference: PRINCE2 7 Foundation resources and study materials.

asked 23/09/2024
Anshul Vyas
45 questions

Question 129

Report Export Collapse

Which document should record the agreed amount of risk budget for a project?

Project Brief
Project Brief
Project Plan
Project Plan
Risk Management Strategy
Risk Management Strategy
Risk Register
Risk Register
Suggested answer: C
Explanation:

The agreed amount of risk budget for a project is recorded in the Risk Management Strategy document. This document outlines how risks will be managed throughout the project, including the budget set aside specifically for implementing risk responses. It provides a structured approach to managing risks, including their identification, assessment, planning responses, and the funds allocated for these activities.

Reference: PRINCE2 7 Foundation handbook and documents.

asked 23/09/2024
Natcha Koopipat
45 questions

Question 130

Report Export Collapse

Which statement describes the 'Implement' step within the recommended risk management procedure?

Take planned action to respond to a risk
Take planned action to respond to a risk
Implement the responsibilities for risks defined in the Risk Management Strategy
Implement the responsibilities for risks defined in the Risk Management Strategy
Assess the proximity of a risk
Assess the proximity of a risk
Identify the level of risks that can be tolerated by the project
Identify the level of risks that can be tolerated by the project
Suggested answer: A
Explanation:

The 'Implement' step within the recommended risk management procedure in PRINCE2 involves taking planned actions to respond to a risk. This step is crucial as it moves the risk response from the planning stage into actual execution, thus addressing the risk directly to mitigate its impact on the project.

Reference: PRINCE2 7 Foundation study guide and official documents.

asked 23/09/2024
EDUARDO LEE
44 questions
Total 463 questions
Go to page: of 47