Question 141

Report
Export
Collapse

Which is a purpose of a Risk Register?

Capture risks that may occur during the project
Capture risks that may occur during the project
Record how risk management activities will be undertaken on the project
Record how risk management activities will be undertaken on the project
Record the risk tolerance for the project
Record the risk tolerance for the project
Capture issues which are impacting on the delivery of the project objectives
Capture issues which are impacting on the delivery of the project objectives
Suggested answer: A

Explanation:

The purpose of a Risk Register in PRINCE2 is to capture all the risks that may impact the project throughout its duration. It serves as a tool to document the details of each identified risk, including their nature, potential impact, and proposed responses. This register is continuously updated as new risks are identified and as existing risks evolve or are resolved.

Reference: PRINCE2 7 Foundation handbook and official documents.

asked 23/09/2024
Derek Steven Schulte
41 questions

Question 142

Report
Export
Collapse

Which role is responsible for ensuring the project is justified in terms of cost?

Project manager
Project manager
Executive
Executive
Senior user
Senior user
Senior supplier
Senior supplier
Suggested answer: B

Explanation:

In PRINCE2, the Executive role is responsible for ensuring that the project is justifiable in terms of cost. This includes making decisions about whether the project remains viable and desirable within its cost constraints. The Executive is tasked with the overall direction and management of the project from a business perspective, ensuring that it delivers value for money.

Reference: PRINCE2 7 Foundation resources and materials.

asked 23/09/2024
Darren Bajada
46 questions

Question 143

Report
Export
Collapse

What is described as an organization's unique attitude towards risk taking

Risk appetite
Risk appetite
Risk management
Risk management
Risk evaluation
Risk evaluation
Risk tolerance
Risk tolerance
Suggested answer: A

Explanation:

An organization's unique attitude towards risk-taking is described as its 'Risk appetite'. Risk appetite defines the level and type of risk that an organization is willing to pursue or retain. This concept is critical in guiding how risks are managed across projects, as it influences decision-making and strategy regarding risk exposure.

Reference: PRINCE2 7 Foundation study guide and official documents.

asked 23/09/2024
Ruben Munilla Hernandez
42 questions

Question 144

Report
Export
Collapse

Which is a purpose of the Risk Register?

Describe the risk management techniques and standards to be applied to the project
Describe the risk management techniques and standards to be applied to the project
Act as a central record of information relating to the identified risks for the project
Act as a central record of information relating to the identified risks for the project
Act as a repository for informal issues
Act as a repository for informal issues
List the responsibilities for achieving an effective risk management procedure
List the responsibilities for achieving an effective risk management procedure
Suggested answer: B

Explanation:

The purpose of the Risk Register in PRINCE2 is to act as a central record of information relating to the identified risks for the project. It includes details about each risk such as their description, probability, impact, and countermeasures. The register helps in monitoring and controlling risks efficiently throughout the project lifecycle.

Reference: PRINCE2 7 Foundation handbook and documents.

asked 23/09/2024
Kristina Stojanovska
42 questions

Question 145

Report
Export
Collapse

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

Controlling a Stage
Controlling a Stage
Closing a Project
Closing a Project
Directing a Project
Directing a Project
Managing a Stage Boundary
Managing a Stage Boundary
Suggested answer: D

Explanation:

The Managing a Stage Boundary process provides the Project Board with information necessary to review the success of the current stage and decide whether there remains a justified business reason to continue with the project. This process includes the evaluation of the stage's performance and the ongoing viability of the project.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
himanshu deshpande
41 questions

Question 146

Report
Export
Collapse

Which is a purpose of the Managing a Stage Boundary process?

Provide the Project Board with sufficient information for approving the next stage
Provide the Project Board with sufficient information for approving the next stage
Approve the next Stage Plan
Approve the next Stage Plan
Review and close any risks and issues identified during the previous stage
Review and close any risks and issues identified during the previous stage
Control the link between the Project Manager and the Team Manager(s)
Control the link between the Project Manager and the Team Manager(s)
Suggested answer: A

Explanation:

The purpose of the Managing a Stage Boundary process is to prepare and provide the necessary information for the Project Board to make an informed decision about authorizing the next stage of the project. This includes the preparation of key documents such as the End Stage Report and the next Stage Plan.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
FOTIS FOURLIAS
47 questions

Question 147

Report
Export
Collapse

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

End Stage Report
End Stage Report
Team Plan
Team Plan
Work Package
Work Package
Project Plan
Project Plan
Suggested answer: D

Explanation:

During the Managing a Stage Boundary process, the Project Plan is updated with the latest estimated costs and time for the upcoming stage. This ensures that the Project Plan reflects current expectations and planning realities as the project progresses.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Mitesh Solanki
47 questions

Question 148

Report
Export
Collapse

Which is an objective of the Starting up a Project process?

Identify who will be responsible for creating the Project Plan
Identify who will be responsible for creating the Project Plan
Agree how the project will be monitored and controlled after initiation
Agree how the project will be monitored and controlled after initiation
Authorize the Project Manager to proceed with the initiation stage
Authorize the Project Manager to proceed with the initiation stage
Agree how issues and changes will be identified, assessed and controlled
Agree how issues and changes will be identified, assessed and controlled
Suggested answer: A

Explanation:

The objective of the Starting up a Project process in PRINCE2 includes ensuring that the roles and responsibilities are defined before the project is formally initiated. This includes identifying who will be responsible for creating the Project Plan.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Brandon O'Driscoll
34 questions

Question 149

Report
Export
Collapse

Which is created during the Starting up a Project process?

Project mandate
Project mandate
Project management team role descriptions
Project management team role descriptions
Communication Management Strategy
Communication Management Strategy
Quality Register
Quality Register
Suggested answer: B

Explanation:

During the Starting up a Project process, one of the key activities is to create role descriptions for the project management team. This ensures that everyone involved understands their responsibilities and the expectations placed upon them before the project commences.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

asked 23/09/2024
Raza Todorovac
44 questions

Question 150

Report
Export
Collapse

Which should be provided by corporate or programme management before the Starting up a Project process commences?

A Project Brief
A Project Brief
Sufficient information to identify the prospective Executive
Sufficient information to identify the prospective Executive
The Project Initiation Documentation
The Project Initiation Documentation
Authority to initiate a project
Authority to initiate a project
Suggested answer: B

Explanation:

Before the Starting up a Project process begins, corporate or programme management should provide sufficient information to identify the prospective Executive. The Executive is a key role within the project board, responsible for overall project direction and management.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.