Which is a purpose of a Risk Register?

A.
Capture risks that may occur during the project
A.
Capture risks that may occur during the project
Answers
B.
Record how risk management activities will be undertaken on the project
B.
Record how risk management activities will be undertaken on the project
Answers
C.
Record the risk tolerance for the project
C.
Record the risk tolerance for the project
Answers
D.
Capture issues which are impacting on the delivery of the project objectives
D.
Capture issues which are impacting on the delivery of the project objectives
Answers
Suggested answer: A

Explanation:

The purpose of a Risk Register in PRINCE2 is to capture all the risks that may impact the project throughout its duration. It serves as a tool to document the details of each identified risk, including their nature, potential impact, and proposed responses. This register is continuously updated as new risks are identified and as existing risks evolve or are resolved.

Reference: PRINCE2 7 Foundation handbook and official documents.

Which role is responsible for ensuring the project is justified in terms of cost?

A.
Project manager
A.
Project manager
Answers
B.
Executive
B.
Executive
Answers
C.
Senior user
C.
Senior user
Answers
D.
Senior supplier
D.
Senior supplier
Answers
Suggested answer: B

Explanation:

In PRINCE2, the Executive role is responsible for ensuring that the project is justifiable in terms of cost. This includes making decisions about whether the project remains viable and desirable within its cost constraints. The Executive is tasked with the overall direction and management of the project from a business perspective, ensuring that it delivers value for money.

Reference: PRINCE2 7 Foundation resources and materials.

What is described as an organization's unique attitude towards risk taking

A.
Risk appetite
A.
Risk appetite
Answers
B.
Risk management
B.
Risk management
Answers
C.
Risk evaluation
C.
Risk evaluation
Answers
D.
Risk tolerance
D.
Risk tolerance
Answers
Suggested answer: A

Explanation:

An organization's unique attitude towards risk-taking is described as its 'Risk appetite'. Risk appetite defines the level and type of risk that an organization is willing to pursue or retain. This concept is critical in guiding how risks are managed across projects, as it influences decision-making and strategy regarding risk exposure.

Reference: PRINCE2 7 Foundation study guide and official documents.

Which is a purpose of the Risk Register?

A.
Describe the risk management techniques and standards to be applied to the project
A.
Describe the risk management techniques and standards to be applied to the project
Answers
B.
Act as a central record of information relating to the identified risks for the project
B.
Act as a central record of information relating to the identified risks for the project
Answers
C.
Act as a repository for informal issues
C.
Act as a repository for informal issues
Answers
D.
List the responsibilities for achieving an effective risk management procedure
D.
List the responsibilities for achieving an effective risk management procedure
Answers
Suggested answer: B

Explanation:

The purpose of the Risk Register in PRINCE2 is to act as a central record of information relating to the identified risks for the project. It includes details about each risk such as their description, probability, impact, and countermeasures. The register helps in monitoring and controlling risks efficiently throughout the project lifecycle.

Reference: PRINCE2 7 Foundation handbook and documents.

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

A.
Controlling a Stage
A.
Controlling a Stage
Answers
B.
Closing a Project
B.
Closing a Project
Answers
C.
Directing a Project
C.
Directing a Project
Answers
D.
Managing a Stage Boundary
D.
Managing a Stage Boundary
Answers
Suggested answer: D

Explanation:

The Managing a Stage Boundary process provides the Project Board with information necessary to review the success of the current stage and decide whether there remains a justified business reason to continue with the project. This process includes the evaluation of the stage's performance and the ongoing viability of the project.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which is a purpose of the Managing a Stage Boundary process?

A.
Provide the Project Board with sufficient information for approving the next stage
A.
Provide the Project Board with sufficient information for approving the next stage
Answers
B.
Approve the next Stage Plan
B.
Approve the next Stage Plan
Answers
C.
Review and close any risks and issues identified during the previous stage
C.
Review and close any risks and issues identified during the previous stage
Answers
D.
Control the link between the Project Manager and the Team Manager(s)
D.
Control the link between the Project Manager and the Team Manager(s)
Answers
Suggested answer: A

Explanation:

The purpose of the Managing a Stage Boundary process is to prepare and provide the necessary information for the Project Board to make an informed decision about authorizing the next stage of the project. This includes the preparation of key documents such as the End Stage Report and the next Stage Plan.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

A.
End Stage Report
A.
End Stage Report
Answers
B.
Team Plan
B.
Team Plan
Answers
C.
Work Package
C.
Work Package
Answers
D.
Project Plan
D.
Project Plan
Answers
Suggested answer: D

Explanation:

During the Managing a Stage Boundary process, the Project Plan is updated with the latest estimated costs and time for the upcoming stage. This ensures that the Project Plan reflects current expectations and planning realities as the project progresses.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which is an objective of the Starting up a Project process?

A.
Identify who will be responsible for creating the Project Plan
A.
Identify who will be responsible for creating the Project Plan
Answers
B.
Agree how the project will be monitored and controlled after initiation
B.
Agree how the project will be monitored and controlled after initiation
Answers
C.
Authorize the Project Manager to proceed with the initiation stage
C.
Authorize the Project Manager to proceed with the initiation stage
Answers
D.
Agree how issues and changes will be identified, assessed and controlled
D.
Agree how issues and changes will be identified, assessed and controlled
Answers
Suggested answer: A

Explanation:

The objective of the Starting up a Project process in PRINCE2 includes ensuring that the roles and responsibilities are defined before the project is formally initiated. This includes identifying who will be responsible for creating the Project Plan.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which is created during the Starting up a Project process?

A.
Project mandate
A.
Project mandate
Answers
B.
Project management team role descriptions
B.
Project management team role descriptions
Answers
C.
Communication Management Strategy
C.
Communication Management Strategy
Answers
D.
Quality Register
D.
Quality Register
Answers
Suggested answer: B

Explanation:

During the Starting up a Project process, one of the key activities is to create role descriptions for the project management team. This ensures that everyone involved understands their responsibilities and the expectations placed upon them before the project commences.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which should be provided by corporate or programme management before the Starting up a Project process commences?

A.
A Project Brief
A.
A Project Brief
Answers
B.
Sufficient information to identify the prospective Executive
B.
Sufficient information to identify the prospective Executive
Answers
C.
The Project Initiation Documentation
C.
The Project Initiation Documentation
Answers
D.
Authority to initiate a project
D.
Authority to initiate a project
Answers
Suggested answer: B

Explanation:

Before the Starting up a Project process begins, corporate or programme management should provide sufficient information to identify the prospective Executive. The Executive is a key role within the project board, responsible for overall project direction and management.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.