PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 16
List of questions
Related questions
Which should be provided by a project mandate?
Why is a Project Brief produced?
Which is a purpose of the Starting up a Project process?
How is the tailoring approach defined for a project?
Which is a purpose of the change theme?
Identify the missing words in the following sentence.
When proposed changes [ ? ], the change authority must refer the decision back to the project board.
Why is a project brief produced?
Which is a key decision made during the 'directing a project' process?
What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
Why can PRINCE2 be applied to any type of project?
Question