ExamGecko
Home Home / PRINCE2 / PRINCE2-7-Foundation

PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 16

Question list
Search
Search

Which should be provided by a project mandate?

A.
Terms of reference
A.
Terms of reference
Answers
B.
Detailed Business Case
B.
Detailed Business Case
Answers
C.
Stage tolerances
C.
Stage tolerances
Answers
D.
Initiation Stage Plan
D.
Initiation Stage Plan
Answers
Suggested answer: A

Explanation:

The project mandate should provide the terms of reference for the project. These define the purpose and objectives of the project, setting the foundation for further project definition and planning in subsequent processes.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Why is a Project Brief produced?

A.
To act as a trigger for the Starting up a Project process
A.
To act as a trigger for the Starting up a Project process
Answers
B.
To record the strategies and management controls to be used by a project
B.
To record the strategies and management controls to be used by a project
Answers
C.
To provide a full and firm foundation for the initiation of a project
C.
To provide a full and firm foundation for the initiation of a project
Answers
D.
To be used by the Project Board as a basis for reviewing the progress of a project
D.
To be used by the Project Board as a basis for reviewing the progress of a project
Answers
Suggested answer: C

Explanation:

A Project Brief is produced to provide a full and firm foundation for the initiation of a project. This document outlines the project's objectives, scope, constraints, expected benefits, and structure of the project management team. It serves as the basis for the next process, Initiating a Project, where more detailed planning and definition of the project take place.

Reference: PRINCE2 7 Foundation handbook and official documents.

Which is a purpose of the Starting up a Project process?

A.
Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate
A.
Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate
Answers
B.
Define the means of communication between the project and corporate or programme management
B.
Define the means of communication between the project and corporate or programme management
Answers
C.
Define the project controls
C.
Define the project controls
Answers
D.
Record any identified risks in the Risk Register
D.
Record any identified risks in the Risk Register
Answers
Suggested answer: A

Explanation:

The purpose of the Starting up a Project process is to provide information so a decision can be made as to whether a project is viable and worthwhile to initiate. This process ensures that the necessary preliminary steps are taken to define the project at a high level and to check that it is sensible to proceed before committing significant resources to the initiation of the project.

Reference: PRINCE2 7 Foundation resources and study materials.

How is the tailoring approach defined for a project?

A.
The project board approves the approach
A.
The project board approves the approach
Answers
B.
The project board documents the approach
B.
The project board documents the approach
Answers
C.
Project assurance approves the approach
C.
Project assurance approves the approach
Answers
D.
Project assurance documents the approach
D.
Project assurance documents the approach
Answers
Suggested answer: A

Explanation:

The tailoring approach for a project is defined and approved by the project board. This includes adapting PRINCE2 to suit the project's environment, size, complexity, importance, capability, and risk. Tailoring is crucial to ensuring that the project management method is applied in a way that fits the specific characteristics of the project and its context.

Reference: PRINCE2 7 Foundation handbook and documents.

Which is a purpose of the change theme?

A.
To prevent change to baselined products
A.
To prevent change to baselined products
Answers
B.
To identify, assess and control any potential and approved changes to baselined products
B.
To identify, assess and control any potential and approved changes to baselined products
Answers
C.
To establish mechanisms to monitor and compare actual achievements against those planned
C.
To establish mechanisms to monitor and compare actual achievements against those planned
Answers
D.
To assess and control uncertainty
D.
To assess and control uncertainty
Answers
Suggested answer: B

Explanation:

The purpose of the Change theme in PRINCE2 is to identify, assess, and control any potential and approved changes to baselined products. This theme provides the mechanisms to manage and control changes, which may affect the project's agreed-upon scope, products, timescales, or costs. It ensures that all changes are assessed for their impact and only implemented with appropriate approvals.

Reference: PRINCE2 7 Foundation resources and materials.

Identify the missing words in the following sentence.

When proposed changes [ ? ], the change authority must refer the decision back to the project board.

A.
are below the agreed change budget
A.
are below the agreed change budget
Answers
B.
are objected to by team members
B.
are objected to by team members
Answers
C.
are rejected by the change authority
C.
are rejected by the change authority
Answers
D.
exceed the agreed change budget
D.
exceed the agreed change budget
Answers
Suggested answer: D

Explanation:

When proposed changes exceed the agreed change budget, the change authority must refer the decision back to the Project Board. This is because changes that exceed the budget may impact the overall project constraints and require higher-level approval to proceed.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Why is a project brief produced?

A.
To act as a trigger for the 'starting up a project' process
A.
To act as a trigger for the 'starting up a project' process
Answers
B.
To record the how the project will communicate with its stakeholders
B.
To record the how the project will communicate with its stakeholders
Answers
C.
To provide a full and firm foundation for the initiation of a project
C.
To provide a full and firm foundation for the initiation of a project
Answers
D.
To be used by the project board as a basis for reviewing the progress of a project
D.
To be used by the project board as a basis for reviewing the progress of a project
Answers
Suggested answer: C

Explanation:

A project brief is produced to provide a full and firm foundation for the initiation of a project. It outlines the project objectives, scope, constraints, and the project management team structure, setting the stage for detailed planning and initiation activities.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Which is a key decision made during the 'directing a project' process?

A.
Select and appoint the project executive
A.
Select and appoint the project executive
Answers
B.
Approve the project manager role description
B.
Approve the project manager role description
Answers
C.
Confirm that the benefits management approach addresses all expected benefits
C.
Confirm that the benefits management approach addresses all expected benefits
Answers
D.
Approve the proposed project mandate
D.
Approve the proposed project mandate
Answers
Suggested answer: C

Explanation:

A key decision made during the 'directing a project' process is to confirm that the benefits management approach addresses all expected benefits. This ensures that the project is aligned with its intended outcomes and that all potential benefits are adequately planned for and tracked.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

What action is taken as part of the 'controlling a stage' process?

1. Create an exception plan

2. Authorize work to be done

3. Take corrective action

4. Obtain approvals for completed products

A.
1 and 2
A.
1 and 2
Answers
B.
2 and 3
B.
2 and 3
Answers
C.
3 and 4
C.
3 and 4
Answers
D.
1 and 4
D.
1 and 4
Answers
Suggested answer: B

Explanation:

As part of the 'controlling a stage' process, the actions taken include authorizing work to be done (2) and taking corrective action (3) as necessary to manage the stage effectively and keep the project on track.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.

Why can PRINCE2 be applied to any type of project?

A.
Because it provides the project manager with procedures for managing project risks and issues
A.
Because it provides the project manager with procedures for managing project risks and issues
Answers
B.
Because it allows each member of the project management team to fully understand their role and responsibilities
B.
Because it allows each member of the project management team to fully understand their role and responsibilities
Answers
C.
Because it separates the management of the project from the specialist work needed to deliver the products
C.
Because it separates the management of the project from the specialist work needed to deliver the products
Answers
D.
Because it provides the project manager with a planning procedure to plan the project more effectively
D.
Because it provides the project manager with a planning procedure to plan the project more effectively
Answers
Suggested answer: C

Explanation:

PRINCE2 can be applied to any type of project because it separates the management of the project from the specialist work needed to deliver the products. This separation allows PRINCE2 to be flexible and adaptable to different industries and project types, as it focuses on the universal aspects of project management rather than specifics of the work content.

Reference: PRINCE2 7 Foundation handbook and official documents.

Total 463 questions
Go to page: of 47