PRINCE2 PRINCE2-7-Foundation Practice Test - Questions Answers, Page 16
List of questions
Question 151
Which should be provided by a project mandate?
Question 152
Why is a Project Brief produced?
Question 153
Which is a purpose of the Starting up a Project process?
Question 154
How is the tailoring approach defined for a project?
Question 155
Which is a purpose of the change theme?
Question 156
Identify the missing words in the following sentence.
When proposed changes [ ? ], the change authority must refer the decision back to the project board.
Question 157
Why is a project brief produced?
Question 158
Which is a key decision made during the 'directing a project' process?
Question 159
What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
Question 160
Why can PRINCE2 be applied to any type of project?
Question